5 Installation

Installation and operation manual

11

RXYSQ6T8Y1B9
VRV IV-S system air conditioner
4P482276-1 – 2017.04

Leak test and vacuum drying

Checking the refrigerant piping involves:
▪ Checking for any leakages in the refrigerant piping.
▪ Performing  vacuum  drying  to  remove  all  moisture,  air  or  nitrogen

in the refrigerant piping.

If  there  is  a  possibility  of  moisture  being  present  in  the  refrigerant
piping  (for  example,  water  may  have  entered  the  piping),  first  carry
out  the  vacuum  drying  procedure  below  until  all  moisture  has  been
removed.

All piping inside the unit has been factory tested for leaks.

Only  field  installed  refrigerant  piping  needs  to  be  checked.
Therefore, make sure that all the outdoor unit stop valves are firmly
closed before performing leak test or vacuum drying.

NOTICE

Make  sure  that  all  (field  supplied)  field  piping  valves  are
OPEN (not outdoor unit stop valves!) before you start leak
test and vacuuming.

For  more  information  on  the  state  of  the  valves,  refer  to

"5.4.3 Checking refrigerant piping: Setup" on page 11

.

5.4.2

Checking refrigerant piping: General
guidelines

Connect the vacuum pump through a manifold to the service port of
all  stop  valves  to  increase  efficiency  (refer  to 

"5.4.3  Checking

refrigerant piping: Setup" on page 11

).

NOTICE

Use  a  2-stage  vacuum  pump  with  a  non-return  valve  or  a
solenoid  valve  that  can  evacuate  to  a  gauge  pressure  of
–⁠100.7 kPa (−⁠1.007 bar)(5 Torr absolute).

NOTICE

Make  sure  the  pump  oil  does  not  flow  oppositely  into  the
system while the pump is not working.

NOTICE

Do not purge the air with refrigerants. Use a vacuum pump
to evacuate the installation.

5.4.3

Checking refrigerant piping: Setup

p< p>

N2

C

b

c

e

a

g

f

d

A

B

a

Pressure reducing valve

b

Nitrogen

c

Weighing scales

d

Refrigerant R410A tank (siphon system)

e

Vacuum pump

f

Liquid line stop valve

g

Gas line stop valve

A

Valve A

B

Valve B

C

Valve C

Valve

State of valve

Valve A

Open

Valve B

Open

Valve C

Open

Liquid line stop valve

Close

Gas line stop valve

Close

NOTICE

The  connections  to  the  indoor  units  and  all  indoor  units
should also be leak and vacuum tested. Keep any possible
(field supplied) field piping valves open as well.

Refer to the indoor unit installation manual for more details.
Leak  test  and  vacuum  drying  should  be  done  before  the
power  supply  is  set  to  the  unit.  If  not,  see  also  the  flow
chart  earlier  described  in  this  chapter  (see 

"5.4.1  About

checking the refrigerant piping" on page 10

).

5.4.4

To perform a leak test

The leak test must satisfy the specifications of EN378‑2.

To check for leaks: Vacuum leak test

1

Evacuate  the  system  from  the  liquid  and  gas  piping  to
–⁠100.7 kPa (–⁠1.007 bar)(5 Torr absolute) for more than 2 hours.

2

Once  reached,  turn  off  the  vacuum  pump  and  check  that  the
pressure does not rise for at least 1 minute.

3

Should  the  pressure  rise,  the  system  may  either  contain
moisture (see vacuum drying below) or have leaks.

To check for leaks: Pressure leak test

1

Break  the  vacuum  by  pressurising  with  nitrogen  gas  to  a
minimum  gauge  pressure  of  0.2  MPa  (2  bar).  Never  set  the
gauge pressure higher than the maximum operation pressure of
the unit, i.e. 4.0 MPa (40 bar).

2

Test  for  leaks  by  applying  a  bubble  test  solution  to  all  piping
connections.

3

Discharge all nitrogen gas.

NOTICE

Make  sure  to  use  a  recommended  bubble  test  solution
from  your  wholesaler.  Do  not  use  soap  water,  which  may
cause cracking of flare nuts (soap water may contain salt,
which  absorbs  moisture  that  will  freeze  when  the  piping
gets  cold),  and/or  lead  to  corrosion  of  flared  joints  (soap
water  may  contain  ammonia  which  causes  a  corrosive
effect between the brass flare nut and the copper flare).

5.4.5

To perform vacuum drying

To remove all moisture from the system, proceed as follows:

1

Evacuate the system for at least 2 hours to a target vacuum of
–⁠100.7 kPa (–⁠1.007 bar)(5 Torr absolute).

2

Check  that,  with  the  vacuum  pump  turned  off,  the  target
vacuum is maintained for at least 1 hour.

3

Should  you  fail  to  reach  the  target  vacuum  within  2  hours  or
maintain  the  vacuum  for  1  hour,  the  system  may  contain  too
much moisture. In that case, break the vacuum by pressurising
with  nitrogen  gas  to  a  gauge  pressure  of  0.05  MPa  (0.5  bar)
and repeat steps 1 to 3 until all moisture has been removed.

4

Depending  on  whether  you  want  to  immediately  charge
refrigerant through the refrigerant charge port or first pre-charge
a  portion  of  refrigerant  through  the  liquid  line,  either  open  the
outdoor  unit  stop  valves,  or  keep  them  closed.  See 

"5.6.3  To

charge refrigerant" on page 13

 for more information.

Summary of Contents for RXYSQ6T8Y1B9

Page 1: ...Installation and operation manual VRV IV S system air conditioner English Installation and operation manual VRV IV S system air conditioner RXYSQ6T8Y1B9...

Page 2: ...1700 1000 500 HU a b 100 100 c d e eB eD A B C D E HB HD A B C 200 300 1000 A B C E 200 300 1000 1000 500 D 1000 D E 1000 1000 500 B D HD HU 300 1000 HD HU 250 1500 HU HD HU 300 1500 B D E HB HD HB H...

Page 3: ...ogojem da se uporabljajo v skladu z na imi navodili on vastavuses j rgmis t e standardi te ga v i teiste normatiivsete dokumentidega kui neid kasutatakse vastavalt meie juhenditele atitinka emiau nuro...

Page 4: ...ng the electrical wiring 14 5 7 4 To connect the electrical wiring on the outdoor unit 14 5 8 Finishing the outdoor unit installation 15 5 8 1 To finish the transmission wiring 15 6 Configuration 16 6...

Page 5: ...nce Authorised installers end users INFORMATION This appliance is intended to be used by expert or trained users in shops in light industry and on farms or for commercial use by lay persons Documentat...

Page 6: ...dity conditions make sure to take precautions to keep the drain holes of the unit free by using proper equipment In heating T AO C WB a b 20 15 5 15 10 5 0 5 10 15 20 10 15 20 2527 30 TAI C DB a Warmi...

Page 7: ...Piping between refrigerant branch kit and indoor unit Use the same diameters as the connections liquid gas on the indoor units The diameters of the indoor units are as follows Indoor unit capacity ind...

Page 8: ...To install the outdoor unit 4 M12 5 2 3 To provide drainage Make sure that condensation water can be evacuated properly Install the unit on a base to make sure that there is a proper drainage in orde...

Page 9: ...alve is now closed Closing direction To handle the stop valve cover The stop valve cover is sealed where indicated by the arrow Do NOT damage it After handling the stop valve tighten the stop valve co...

Page 10: ...open the stop valves after installing the refrigerant piping and performing vacuum drying Running the system with the stop valves closed may break the compressor 5 4 Checking the refrigerant piping 5...

Page 11: ...fer to the indoor unit installation manual for more details Leak test and vacuum drying should be done before the power supply is set to the unit If not see also the flow chart earlier described in th...

Page 12: ...e finished properly NOTICE Be sure to turn on the power 6 hours before operation in order to have power running to the crankcase heater and to protect the compressor NOTICE If operation is performed w...

Page 13: ...y operating the outdoor unit by means of the manual additional refrigerant charge mode 5 Connect as shown Make sure valve A is closed p p R410A a c d b A d a Weighing scales b Refrigerant R410A tank s...

Page 14: ...unit near the gas and liquid stop valves 5 7 Connecting the electrical wiring 5 7 1 Field wiring Overview Field wiring consists of power supply always including earth and indoor outdoor communication...

Page 15: ...3 1 a Power supply cable b Transmission wiring cable Connecting to the frame When cables are routed from the unit a protection sleeve for the conduits PG insertions can be inserted at the knockout hol...

Page 16: ...or special operation e g 1 time operation recovery vacuuming setting manual adding refrigerant setting etc In such a case it is required to abort the special operation before normal operation can rest...

Page 17: ...iring Switching between modes Use BS1 to switch between the default situation mode 1 and mode 2 B S 1 5 s B S 1 B S 1 B S 1 a c b a Default situation H1P OFF b Mode 1 H1P flashing c Mode 2 H1P ON BS1...

Page 18: ...an optional accessory is required Value Description H7P Shows the status of power consumption limitation operation OFF Unit is currently not operating under power consumption limitations ON Unit is c...

Page 19: ...gerant charge amount in a manual way without automatic refrigerant charging functionality following setting should be applied default Deactivated Activated To stop the manual additional refrigerant ch...

Page 20: ...al signal is sent to the unit this setting defines the level power consumption limitation that will be applied for step 1 The level is according to the table 60 default 70 80 2 31 Power consumption li...

Page 21: ...t correspond to the voltage on the identification label of the unit Earth wiring Be sure that the earth wires have been connected properly and that the earth terminals are tightened Insulation test of...

Page 22: ...Under centralised control will display on the user interface of indoor units Steps during the automatic system test run procedure Step Description Control before start up pressure equalisation Coolin...

Page 23: ...Suction temperature sensor malfunction R3T A1P X12A R5T A1P X12A Check connection on PCB or actuator Liquid temperature sensor coil malfunction R4T A1P X12A Check connection on PCB or actuator Liquid...

Page 24: ...allowed Multiple rows of units See figure 2 on the inside of the front cover Stacked units max 2 levels See figure 3 on the inside of the front cover A1 A2 A1 If there is danger of drainage dripping...

Page 25: ...2P Printed circuit board inverter BS Push buttons mode set return test reset A1P C Capacitor A2P DS1 DIP switch A1P F1U F2U Fuse T 31 5 A 500 V A1P F1U Fuse T 5 0 A 250 V A2P F3U F4U F5U Fuse T 6 3 A...

Page 26: ...ay be put in action and the air conditioner may not operate Above operation range is only valid in case direct expansion indoor units are connected to the VRV IV S system 12 2 Operating the system 12...

Page 27: ...emperature decrease minimal room cooling The micro computer automatically determines temperature and fan speed cannot be set by the user interface The system does not go into operation if the room tem...

Page 28: ...essary to designate one of the user interfaces as the master user interface The displays of slave user interfaces show change over under centralised control and slave user interfaces automatically fol...

Page 29: ...s gas cookers etc is present Always have qualified service personnel confirm that the point of leakage has been repaired or corrected before resuming operation 14 Troubleshooting If one of the followi...

Page 30: ...over current detected Main code Contents Compressor lock startup Transmission outdoor unit inverter INV transmission trouble INV unbalanced power supply voltage Fin thermistor malfunction Capacity se...

Page 31: ...ystem stops after heating operation Expansion and contraction of plastic parts caused by temperature change make this noise A low sah choro choro sound is heard while the indoor unit is stopped When a...

Page 32: ...4P482276 1 2017 04 Copyright 2017 Daikin 4P482276 1 0000000R...