![background image](http://html1.mh-extra.com/html/daikin/rxf50a2v1b/rxf50a2v1b_installation-manual_2459908008.webp)
4 Installation
Installation manual
8
RXF50+60A2V1B
R32 split series
3P512025-3 – 2017.11
20 mm
330
580
240
(mm)
240
>300
In any case, provide at least
300
mm of free space below the unit.
Additionally, make sure the unit is positioned at least
100
mm above
the maximum expected level of snow. In this case, it is
recommended to construct a pedestal.
330
580
240
240
(mm)
>300
100
a
a
Maximum snowfall height
If the unit is installed on brackets to the wall, install the unit as
follows:
>250
>300
>100
(mm)
a
a
Maximum snowfall height