background image

RR+RQ71+10 RR+RQ71~125B7W1B
Split System air conditioners
4PW19370-1C

Installation manual

4

I

NSTALLATION

 

SERVICING

 

SPACE

The numerical figures used in here represent the dimensions for the
71-100-125 class models. Figures between (  ) indicate the
dimensions for the 100-125 class models. (Unit: mm)

(Refer to 

"Precautions on installation" on page 3

)

Precaution

(A) In case of non-stacked installation 

(See figure 1)

(B) In case of stacked installation

1.

In case obstacles exist in front of the outlet side.

2.

In case obstacles exist in front of the air inlet.

Do not stack more than one unit.

About 100 mm is required as the dimension for laying the upper
outdoor unit's drain pipe. Get the portion A sealed so that air from the
outlet does not bypass.

(C) In case of multiple-row installation (for roof top use, etc.)

1.

In case of installing one unit per row.

2.

In case of installing multiple units (2 units or more) in lateral
connection per row.

Relation of dimensions of H, A and L are shown in the table below.

R

EFRIGERANT

 

PIPE

 

SIZE

 

AND

 

ALLOWABLE

 

PIPE

 

LENGTH

Selection of piping material

Construction material: phosphoric acid deoxidized seamless
copper for refrigerant.

Temper grade: use piping with temper grade in function of the
pipe diameter as listed in table below.

The pipe thickness of the refrigerant piping should comply with
relevant local and national regulations. The minimal pipe
thickness for R-410A piping must be in accordance with the
table below.

O=Annealed
1/2H=Half hard

Suction side obstacle

Obstacle is present

Discharge side obstacle

1

In these cases, close the 
bottom of the installation 
frame to prevent the 
discharged air from 
being bypassed

Left side obstacle

Right side obstacle

2

In these cases, only 2 
units can be installed.

Top side obstacle

This situation is not 
allowed

1000

100

A

200

(300)

100

A

500

100

(200)

1000

50

(100)

L

A

L

H

0<L

1/2H

150 (250)

1/2H<L

200 (300)

H<L

Installation impossible

All field piping must be installed by a licensed refrigeration
technician and must comply with relevant local and
national regulations.

NOTE

To persons in charge of piping work:

Be sure to open the shut-off valve after installing
piping and vacuming is complete. (Running the
system with the valve closed may break the
compressor.)

It is forbidden to discharge refrigerant into the
atmosphere. Collect the refrigerant in accordance
with relevant local and national regulations.

Do not use flux when brazing the refrigerant piping.
For brazing, use phosphor copper brazing filler metal
(BCuP) which does not require a flux.
(If a chlorine flux is used, the piping will corrode, and if
the flux contains fluoride, it will cause the coolant oil to
deteriorate, adversely affecting the coolant piping
system.)

Pipe Ø

Temper grade of piping 

material

Minimal thickness t(mm)

9.5

O

0.80

15.9

O

1.20

19.1

1/2H

1

1000

400 (600)

2000

A

H

L

Summary of Contents for RQ100B7V3B

Page 1: ...INSTALLATION MANUAL RR71B7V3B RR100B7V3B RR71B7W1B RR100B7W1B RR125B7W1B RQ71B7V3B RQ100B7V3B RQ71B7W1B RQ100B7W1B RQ125B7W1B Split System air conditioners...

Page 2: ...1 1 2 4 5 2 4 5 9 7 6 6 8 3 3 1 3 2 4 5 A B A E B C D H H1 L1 H1 H2 L3 L1 L2 H1 H2 L4 L1 L3 L2 A A B2 B2 B2 C C D1 D1 D1 D2 D2 D2 D2 D2 E E H H L1 L1 L1 L2 L2 L2 A A B1 B1 B1 B1 B1 B1 B2 B2 B2 C C D1...

Page 3: ...zate n conformitate cu instruc iunile noastre 19 skladni z naslednjimi standardi in drugimi normativi pod pogojem da se uporabljajo v skladu z na imi navodili 20 on vastavuses j rgmis t e standardi te...

Page 4: ...m not exceeding the limit please consult with your distributor If the leaked amount exceeds the limit it may cause an oxygen deficiency accident Be sure to use only the specified accessories and parts...

Page 5: ...ning conductor or telephone earth wire Incomplete grounding may cause electric shocks Gas pipe Ignition or explosion may occur if the gas leaks Water pipe Hard vinyl tubes are not effective grounds Li...

Page 6: ...a foundation of concrete blocks etc the height of the foundation should be maximum 150 mm 5 If you install the unit on a frame please install a waterproof plate within 150 mm of the underside of the...

Page 7: ...omply with relevant local and national regulations The minimal pipe thickness for R 410A piping must be in accordance with the table below O Annealed 1 2H Half hard Suction side obstacle Obstacle is p...

Page 8: ...g cure the piping with a pinch or taping Great caution is needed when passing copper tubes through walls In case of simultanious operating system Upward and downward piping should be performed at the...

Page 9: ...only a torque wrench is used when loosening or tightening flare nuts always lock the shut off valve with a wrench and then use a torque wrench Do not place wrenches on the valve cover Do not apply fo...

Page 10: ...e and outside and first screw the nut 3 or 4 turns by hand Coat here with ether or ester oil After completing the installation carry out a gas leak inspection of the piping connections with nitrogen a...

Page 11: ...t 4 Weighing machine 5 Vacuum pump 6 Stop valve 7 Main pipe 8 Branched pipes 9 Pipe branching kit optional 1 Evacuate the pipes and check vacuum 1 No pressure increase for 1 minute 1 Use a 2 stage vac...

Page 12: ...uming can not be executed completely using such port Position of service port Heat pump Heat pump units have 2 ports on the piping One between the liquid receiver and the electronic expansion valve an...

Page 13: ...cover securely 1 Switch box 2 Stop valve mounting plate 3 Ground 4 Power supply and ground wiring 5 Wiring between units 6 Tie wrap When cables are routed from the unit a protection sleeve for the co...

Page 14: ...appens turn off the power re check the wiring and switch the position of two of the three electrical wires If operation is not possible do not under any circumstances force the electromagnetic contact...

Page 15: ...circuit R1T Thermistor air R2T Thermistor coil R3T Thermistor discharge RC Signal receiver circuit S1PH Pressure switch HIGH S1PL Pressure switch LOW SD Safety devices input T1A Transformer 220 240 V...

Page 16: ...Zandvoordestraat 300 B 8400 Oostende Belgium 4PWEN19370 1C...

Reviews: