R(Y)P200+250B8W1
Split System air conditioners
4PW23688-1B

Installation manual

5

Leak test

1.

Evacuate the pipes and check vacuum. (No pressure increase for 1
minute.)

2.

Break the vacuum with a minimum of 2 bar of nitrogen.

3.

Conduct leak test by applying soap water, etc. to the connecting part
of the pipes.

4.

Discharge Nitrogen.

5.

Evacuate and check vacuum again.

6.

Open the stop valve and inject the refrigerant into the refrigerant pipe
and into the indoor unit.

7.

Leak test must satisfy EN 378-2.

C

HARGING

 

REFRIGERANT

Important information regarding the refrigerant used

This product contains fluorinated greenhouse gases covered by the
Kyoto Protocol. Do not vent gases into the atmosphere.

Refrigerant type:

R407C

GWP

(1)

 value:

1652.5

(1)

 GWP = global warming potential

Please fill in with indelible ink,

 the factory refrigerant charge of the product,

 the additional refrigerant amount charged in the field and

+

➁ 

the total refrigerant charge

on the refrigerant charge label supplied with the product.

The filled out label must be adhered in the proximity of the product
charging port (e.g. onto the inside of the service cover).

This unit requires additional charging of refrigerant according to the
length of pipe connected at the site. Concerning R407C refrigerant:
charge the refrigerant to the liquid pipe in its liquid state. Since
R407C is a mixed refrigerant, its composition changes if charged in a
state of gas and normal system operation would no longer be
assured.

Concerning L1~L7 (see tables below), refer to figures 

2

~

5

.

Additional charging of refrigerant

Find the correct amount of additional refrigerant to charge ‘G’ (kg)
using one of the following formulas.

If G<0: no addition is required.

Pair system: refer to 

figure 2

L1 (m)

one way length of liquid pipe

Simultaneous operation system
(Twin, Triple, Double Twin: refer to figures 

2

~

5

)

L1 (m)

one way length of main liquid pipe

L2~L7 (m) one way length of branched liquid pipes

Complete charging of the refrigerant

When the entire refrigerant pipe length is within 30 m, charge the
refrigerant in accordance with the amount mentioned in the
nameplate and when the pipe length exceeds 30 m, the charging
amount mentioned in the nameplate and that required for additional
charging are to be totaled as the net charging amount.

Precaution for pumping-down operation

The outdoor unit is equipped with a low-pressure switch to protect the
compressor. Take the following steps to perform the pumping-down
operation.

1.

Start the fan operation with the remote controller.
Confirm that stop valves both on the liquid and gas side are open.

2.

Push the pumping-down button on the PC board of the outdoor unit
during more than 5 seconds.
Compressor and outdoor fan will start operation automatically.
If step 2 is performed before step 1, then the indoor fan may
automatically start running. Please pay attention to this.

3.

Continue operation for 2 min. until operation condition stabilizes.

4.

Close the stop valve on the liquid side securely. 

(See "Operating stop

valve: refer to figure 7".)

Insecure closing of the valve may result in burning of the
compressor.

5.

When the low-pressure switch is activated, the unit stops working. At
this time, close the stop valve on the gas side.

This is the end of pumping-down operation. After pumping-down
operation, the remote controller can show the following pattern:

“U4”

blank screen

indoor fan operates for about 30 sec.

even when ON button on the remote controller is pressed, and it will
not operate. Turn off the main power supply switch and turn it on
again in need of operation.

1

factory refrigerant charge 
of the product:
see unit name plate

2

additional refrigerant 
amount charged in the 
field

3

total refrigerant charge

4

Contains fluorinated 
greenhouse gases 
covered by the Kyoto 
Protocol

5

outdoor unit

6

refrigerant cylinder and 
manifold for charging

3

5

6

2

1

4

RP200

G=(L1–30)x0.06

RP250

G=(L1–30)x0.09

RYP200

G=(L1–30)x0.10

RYP250

G=(L1–30)x0.14

RP200

G=(L1–30)x0.06+L2xA+L3xA+L4xA+L5xA+L6xA+L7xA

RP250

G=(L1–30)x0.09+L2xA+L3xA+L4xA+L5xA+L6xA+L7xA

RYP200

G=(L1–30)x0.10+L2xA+L3xA+L4xA+L5xA+L6xA+L7xA

RYP250

G=(L1–30)x0.14+L2xA+L3xA+L4xA+L5xA+L6xA+L7xA

Branched pipe

A

RP200+250

Ø9.5

0.03 kg/m

250

Ø6.4

0.03 kg/m

Ø9.5

0.05 kg/m

Never short-circuit the low-pressure switch in this operation.
In order to avoid electric shock, please put the insulation
sheet as follows. 

(See figure 9)

.

1

Switch box

2

PCB

3

Pump down button

4

Insulation sheet

5

Tape

Summary of Contents for RP200B8W1

Page 1: ...INSTALLATION MANUAL RP200B8W1 RP250B8W1 RYP200B8W1 RYP250B8W1 Split System air conditioners...

Page 2: ...500 Y B1 300 Y 2 H 1500 A 500 h 500 B2 100 H 1500 X A 500 X 2 h 500 Y B2 100 Y 2 h H A B1 B2 mm 10 10 10 20 20 B1 A B2 A 50 50 50 50 100 100 B2 A 2 2 H1 L1 3 3 H1 H2 L3 L1 L2 4 4 H1 H2 L4 L1 L3 L2 5...

Page 3: ...ck konstrukce A a pozitivn zji t no B v souladu s osv d en m C jak bylo uvedeno v souboru technick konstrukce D a pozitivn zji t no E pou it modul F G Kategorie rizik H Viz tak n sleduj c strana 15 ka...

Page 4: ...n Minim l temperat ra zem spiediena pus L C TSmax Pies tin t temperat ra saska ar maksim lo pie aujamo spiedienu PS M C Dzesin t js N Spiediena dro bas ier ces iestat ana P bar Izgatavo anas numurs un...

Page 5: ...operation system Refer to catalogues for details Never operate the unit without the thermistor R3T burning of the compressor may result When closing the service panels take care that the tightening to...

Page 6: ...et The unit must be installed on a solid longitudinal foundation steelbeam frame or concrete Maximum height of the foundation is 150 mm Lift the unit from the pallet and place it on its installation p...

Page 7: ...screw keys 2 Turn it all the way until the shaft stops 3 Tighten the cap firmly To close 1 Remove the cap and turn the shaft clockwise 2 Tighten the shaft firmly until it reaches the sealed area 4 of...

Page 8: ...vacuum pump which can evacuate to 100 7 kPa 5 Torr 755 mm Hg Evacuate the system from the liquid and gas pipes by using a vacuum pump for more than 2 hours and bring the system to 100 7 kPa After kee...

Page 9: ...e length exceeds 30 m the charging amount mentioned in the nameplate and that required for additional charging are to be totaled as the net charging amount Precaution for pumping down operation The ou...

Page 10: ...power supply line See figure 10 TEST OPERATION For the test run procedure refer to the indoor unit installation manual DISPOSAL REQUIREMENTS Dismantling of the unit treatment of the refrigerant of oil...

Page 11: ...X1M TERMINAL STRIP Y1R 4 WAY VALVE A3P PRINTED CIRCUIT BOARD DS2 SELECTOR SWITCH VARIOUS SEE PCB DS3 SELECTOR SWITCH EMERGENCY HAP LIGHT EMITTING DIODE GREEN H1P H2P LIGHT EMITTING DIODE RED R3T THERM...

Page 12: ...NOTES NOTES...

Page 13: ...8 8 2 4 5 6 2 4 5 7 9 8 6 9 9 1 2 3 3 5 5 4 10 10 3 N 50 Hz 400 V 1 2 3 11 11 1 3 2 4 5...

Page 14: ...Zandvoordestraat 300 B 8400 Oostende Belgium 4PW23688 1B...

Reviews: