8 .  Precautions on refrigerant piping

• 

Do not allow anything other than the designated refrigerant to get 

mixed into the refrigerant cycle, such as air, nitrogen, etc. If any 

refrigerant gas leaks while working on the unit, ventilate the room 
thoroughly right away.

• 

Use R410A only when adding refrigerant.

• 

Installation tools:
Make sure to use installation tools (gauge manifold, charge hose, 

etc.) that are exclusively used for R410A installations to withstand 

the pressure and to prevent foreign materials (e.g., mineral oils and 

moisture) from mixing into the system.

• 

Vacuum pump:

 

- Use a 2-stage vacuum pump with a non-return valve.

 

-

Make sure the pump oil does not flow oppositely into the system 

while the pump is not working.

 

- Use a vacuum pump which can evacuate to 500 microns.

Protection against contamination when installing pipes

Take measures to prevent foreign materials like moisture and contami-

nation from mixing into the system.

Installation

Protection method

More than a month

Pinch the pipe

Less than a month

Pinch or tape pipe

Regardless of the period

Block all gaps in the holes for passing out piping and wiring using seal-

ing material (field supply) (the capacity of the unit will drop and small 

animals may enter the machine).

Example:

 passing piping out through the front.

1

1  Close the areas marked with 

(When the piping is routed from the 
front panel.) 

• 

Use clean pipes only.

• 

Hold the pipe end downwards when removing burrs.

• 

Cover the pipe end when inserting it through a wall so that no dust 
or dirt enters the pipe.

 NOTE

• 

After all the piping has been connected, make sure there is no gas 
leak. Use Dry Nitrogen to perform a gas leak detection.

• 

After knocking out the holes, we recommend you remove burrs in 
the knock holes and paint the edges and areas around the edges 
using the repair paint.

8 .1 .  Caution for brazing

• 

Make sure to blow through with Dry Nitrogen when brazing. Blowing 
through with Dry Nitrogen prevents the creation of large quantities 

of oxidized film on the inside of the piping. An oxidized film ad

-

versely affects valves and compressors in the refrigerating system 
and prevents proper operation.

• 

The Dry Nitrogen pressure should be set to 2.9 psi (0.02 MPa (i.e., 
just enough so it can be felt on the skin)) with a pressure-reducing 
valve.

1

2

3

4

5

6

6

1  Refrigerant piping
2  Part to be brazed
3  Taping
4  Hands valve
5  Pressure-reducing valve
6  Dry Nitrogen

Do not use anti-oxidants when brazing the pipe joints. Residue can 

clog pipes and break equipment:

•  Do not use flux when brazing copper-to-copper refrigerant piping. 

Use phosphor copper brazing filler alloy (BCuP) which does not 
require flux.

•  Flux has an extremely harmful influence on refrigerant piping 

systems. For instance, if chlorine based flux is used, it will cause 
pipe corrosion or, in particular, if the flux contains fluorine, it will 

deteriorate the refrigerant oil.

8 .2 .  Connecting the refrigerant piping

8 .2 .1 . 

Decide front or side (bottom) connection

Installation of refrigerant piping is possible as front connection or side con-

nection (when taken out from the bottom) as shown in the figure below.

1

2

3

1  Left-side connection
2  Front connection
3  Right-side connection

• 

For side connections, the knockout hole on the bottom plate should 
be removed:

3

2

1

1

4

1

Knockout hole (Piping)

2

Drill

3

Points for drilling

4

Knockout hole (Power supply 
wiring)

 NOTE

Precautions when knocking out knockout holes:

• 

Be sure to avoid damaging the casing.

• 

After knocking out the knockout holes, we recommend you remove 
the burrs and paint the edges and areas around the edges using 
repair paint to prevent rusting.

• 

When passing electrical wiring through the knock holes, protect the wir-
ing with a conduit or bushings, making sure not to damage the wiring.

8 .2 .2 .  Remove the pinched pipes

 WARNING

Any gas or oil remaining inside the stop valve may blow off the pinched 
piping.
Failure to observe the instructions in procedure below properly may 
result in property damage or personal injury, which may be serious 
depending on the circumstances.

01_EN_3P362438-9N.indb   14

12/11/2019   2:35:35 PM

Summary of Contents for REYQ72TAYC Series

Page 1: ...event of conflicting information the online installation instruction is to be used Veuillez visiter http www daikinac com content resources manuals pour obtenir la version la plus r cente des instruc...

Page 2: ...nnel must carry out the installation work Installation must be done in accordance with this installation manual Improper installation could result in water leakage electric shock or fire When installi...

Page 3: ...only Outdoor units can be installed either outdoors or indoors This unit is for indoor use Do not install the air conditioner or heat pump in the fol lowing locations a Where a mineral oil mist or oil...

Page 4: ...piping 14 8 1 Caution for brazing 14 8 2 Connecting the refrigerant piping 14 8 3 Guidelines for handling stop valve 17 9 Field wiring 18 9 1 Power circuit safety device and cable requirements 19 9 2...

Page 5: ...Q 192 384 consists of multiple REYQ 72 168 modules as indi cated 72 96 120 144 168 REYQ72TAYC 1 REYQ96TAYC 1 REYQ120TAYC 1 REYQ144TAYC 1 REYQ168TAYC 1 REYQ192TAYC 2 REYQ216TAYC 1 1 REYQ240TAYC 2 REYQ2...

Page 6: ...y For additional information see technical engineering data 1 4 Scope of the manual This manual describes the procedures for handling installing and connecting the VRV IV REYQ T series outdoor units T...

Page 7: ...nough to support the weight of the unit Installation location is flat to prevent vibrations and noise generation and to have sufficient stability The space around the unit is adequate for maintenance...

Page 8: ...mproper installation may result in the unit turning over 4 2 Weather related precautions Be sure that the air inlet of the unit is not positioned towards the main wind direction Frontal wind will dist...

Page 9: ...igure below and choose one of the possibilities a b a c d a b a e d e c a b a e d f c a b a e b d c a b a e d f c 1 2 3 5 4 ABCD Sides along the installation site with obstacles Suction side A B C D A...

Page 10: ...ions can be found in the Engineering Data Book 6 Inspecting handling and unpacking the unit 6 1 Inspection At delivery the unit must be checked and any damage must be re ported immediately to the carr...

Page 11: ...tion bolts until their length remains 13 16 in 20 mm above the foundation surface A A 13 16 in 20 mm NOTE There are restrictions on the refrigerant pipe connecting order between outdoor units in the...

Page 12: ...ational regulations After piping work is complete do not under any circumstances open the stop valve until 9 Field wiring on page 18 and 12 Checking of device and installation conditions on page 24 ar...

Page 13: ...in 34 9 mm 7 3 2 Piping between refrigerant branch kits or refrigerant branch kits and Branch Selector units D Choose from the following table in accordance with the indoor unit total capacity connect...

Page 14: ...Indoor unit capacity index Kit name for 3 pipes for 2 pipes 72 KHRP25M33H9 KHRP25M33HA KHRP26M22H9 KHRP26M22HA maximum 4 indoor units or KHRP26M33H9 KHRP26M33HA maximum 8 indoor units 72 111 KHRP26M33...

Page 15: ...ing length from the first outdoor unit multi connection piping kit to the outdoor unit 33 ft 10 m Equivalent piping length from the first outdoor unit multi connection piping kit to the outdoor unit 4...

Page 16: ...e as fol lows 3 8 in 9 5 mm 1 2 in 12 7 mm 1 2 in 12 7 mm 5 8 in 15 9 mm 5 8 in 15 9 mm 3 4 in 19 1 mm 3 4 in 19 1 mm 7 8 in 22 2 mm C REFNET joints G b d m B f A c D 9 H e g 6 h n F i 4 Outdoor unit...

Page 17: ...vents the creation of large quantities of oxidized film on the inside of the piping An oxidized film ad versely affects valves and compressors in the refrigerating system and prevents proper operation...

Page 18: ...he burner flame Liquid pipe stop valve Suction gas pipe stop value Protective plate Stop valves mounting plate High low pressure gas pipe stop valve 5 Cut off the lower part of the smaller pinched pip...

Page 19: ...of the installer field piping 8 2 4 Precautions when connecting piping between outdoor units multiple outdoor units system To connect the piping between outdoor units an optional multi connection pip...

Page 20: ...ally or vertically Mount the REFNET header so that it branches horizontally 2 Installation of the multi connection piping kit A 1 B 1 C D 15 C 4 3 4 in 120 mm D 19 11 16 in 500 mm Install the joints h...

Page 21: ...refer to 8 3 2 How to use the stop valve Check for refrigerant leaks after tightening the service port cover 9 Field wiring NOTE All field wiring and components must be installed by a licensed elec tr...

Page 22: ...z f3 60Hz f3 60Hz f3 60Hz f3 60Hz f3 60Hz f3 60Hz f3 60Hz f3 60Hz f3 60Hz f3 60Hz f3 60Hz f3 60Hz 575V 575V 575V 575V 575V 575V 575V 575V 575V 575V 575V 575V 575V 575V 15 1 16 8 18 2 22 3 24 9 16 8 16...

Page 23: ...multi system And the other units are Sub unit In this figure outdoor unit A is the Master unit Check operation in installation work onsite settings and so on are done by operating the printed circuit...

Page 24: ...e accessory CAUTION Be sure to use crimp style terminal with insulating sleeves for con nections See the figure below Crimp style terminal Insulating sleeve Power wire For wiring use the designated po...

Page 25: ...OTE Always use nitrogen gas for the air tightness test Absolutely do not open the stop valve until the main power circuit insulation measurement has been completed Measuring after the stop valve is op...

Page 26: ...ze the system to 375 000 microns vacuum break with nitrogen gas and evacuate the system again using the vacuum pump for 1 hour to 500 microns or less vacuum drying If the system cannot be evacuated to...

Page 27: ...e front panel see figure Now you can open the inspection door of the control box cover see figure You can see 3 push buttons and 3 seven segment displays and DIP switches 3 1 2 1 Front panel 2 Inspect...

Page 28: ...indoor units which are con nected to the system Result mode 1 setting 10 is addressed and selected return value is monitored information To leave the monitoring function push BS1 one time you will re...

Page 29: ...ing the additional refrigerant charge In case recharge is required refer to the nameplate of the unit It states the type of refrigerant and necessary amount 14 2 Calculating the additional refrigerant...

Page 30: ...s BS4Q54T 1 BSQ60T 1 BSQ96T 1 Indoor units FXMQ type 18 1 24 1 36 1 54 2 FXFQ type 36 2 Other 48 1 Liquid piping a f3 4 60 ft e f1 4 15 ft i f3 8 20 ft m f3 8 15 ft r f1 2 10 ft b f5 8 20 ft f f3 8 10...

Page 31: ...is a mixed refrigerant adding it in gas form may cause the refrigerant composition to change preventing normal operation Before charging check whether the refrigerant cylinder is equipped with a sipho...

Page 32: ...d stop valve service port open valve C Make sure that all outdoor unit stop valves as well as valves A and C are closed 1 2 3 4 5 6 B 9 8 11 11 12 10 14 13 15 16 A C 7 1 Pressure reducing valve 2 Nitr...

Page 33: ...top valves after pre charging the refrigerant Operating with the stop valves closed will damage the compressor 15 Start up and configuration INFORMATION It is important that all information in this ch...

Page 34: ...e selected time frames The second method is to enable low noise operation based on an external input For this operation an optional acces sory is required 1 2 shows the status of power consumption lim...

Page 35: ...ly be effective when the optional external control adaptor DTA104A61 62 is installed Default value 0 To activate this function change 2 12 1 2 18 Fan high static pressure setting In order to increase...

Page 36: ...tation If the system always needs to run under power consump tion limitation conditions this setting activates and defines the level power consumption limitation that will be applied continuously The...

Page 37: ...e target temperature upper limit Default value 1 Value 2 92 Te target temperature upper limit 0 L 1 M 2 H If Auto Te then use this setting to address different load pro files If the frequent operation...

Page 38: ...ting 2 8 and 2 47 To activate the powerful comfort setting under heating opera tion change field setting 2 82 3 This setting is used in conjunction with setting 2 9 Quick Overshoot during heating oper...

Page 39: ...D E F A Indoor unit set temperature B Operation start C Operating time D Mild E Quick F Powerful Example Automatic mode during cooling A B 100 70 E Tc C D 120 F 49 C F 115 F 46 C 36 F 2 C A Virtual lo...

Page 40: ...MATION Note that during the first running period of the unit required power in put may be higher This phenomenon originates from the compressor that requires a 50 hour run elapse before reaching smoot...

Page 41: ...ion code which is displayed on the outdoor unit will indi cate a main malfunction code and a sub code The sub code indicates more detailed information about the malfunction code The malfunc tion code...

Page 42: ...ction R10T A1P X29A Check connection on printed circuit board or actuator J6 01 02 03 Temperature sensor malfunction R11T A7P X15A Check connection on printed circuit board or actuator 08 09 10 Temper...

Page 43: ...iring between units Check indoor unit amount and total capacity con nected Check connection U9 01 System mismatch Wrong type of indoor units com bined R407C Mini split etc Indoor unit malfunction Chec...

Page 44: ...Pull out junction connectors X1A X2A X3A X4A for the fan motors in the outdoor unit before starting service operation on the inverter equipment Be careful not to touch the live parts If a fan rotates...

Page 45: ...tions and standards for the maximum allowable concentration level is required 2 1 1 Direction of the refrigerant flow 2 Room where refrigerant leak has occurred outflow of all the refrigerant from the...

Page 46: ...Daikin Texas Technology Park 19001 Kermier Road Waller TX 77484 U S A 3P362438 9N EM16A003B 1912 HT 00_CV_3P362438 9N indd 2 2019 09 12 11 44 31...

Reviews: