Outdoor Unit - RXL25G2V1B
Removal Procedure
221
4.3
Removal of PCB
Procedure
Warning
Be sure to wait 10 minutes or more after turning off all power supplies
before disassembling work.
Step
Procedure
Points
1
Remove the screw and
remove the electrical
box cover.
Preparation
Remove the panels
according to the “Removal of
Outer Panels”.
Remove the electrical box
according to the “Removal of
Electrical Box”.
2
Detach the insulation
sheet.
The trimmed part goes front.
3
Remove the 2 screws
of the earth terminals.
(R12274)
Electrical box cover
(R8156)
(R8157)
Insulation
sheet
Earth
terminals
(R8158)
SIENBE04-925_A_FRONT.pdf 236
24/02/2011 13:54:14
Summary of Contents for Inverter FTXL20G2V1B
Page 8: ...SiENBE04 925_A vi Table of Contents...
Page 14: ...Introduction SiENBE04 925_A xii...
Page 15: ...SiENBE04 925_A List of Functions 1 Part 1 List of Functions 1 Functions 2...
Page 17: ...SiENBE04 925_A Specifications 3 Part 2 Specifications 1 Specifications 4...
Page 20: ...Specifications SiENBE04 925_A 6 Specifications...