5

Selecting a location in cold climates

Prevent exposure to wind:

Install the unit with its air intake side facing the wall. Never
install the unit at a site where the air intake side may be
exposed directly to wind.

Install a baffle plate on the air exhaust side of the unit.

In heavy snowfall areas, select an installation site where the
snow will not affect the unit.

Make sure to protect the water circuit against freezing. Refer to

"Protecting the water circuit against freezing" on page 7

.

Unit installation drawing

Indicated distances must be respected to ensure optimal operation of
the unit. For ease of access at the moment of installation or servicing,
the unit may be pushed further away from walls or obstacles.

Inspecting, handling and unpacking the unit

The unit is packed in a cardboard box fixed by straps.

At delivery, the unit should be checked and any damage should
be reported immediately to the carrier claims agent.

Check if all unit accessories (see 

"Accessories" on page 2

) are

enclosed.

Bring the unit as close to its final installation position in its
original package to prevent damage during transport.

After unpacking, the unit can be positioned correctly using the
handles provided at both ends of the unit.

Important information regarding the 
refrigerant used

This product contains fluorinated greenhouse gases covered by the
Kyoto Protocol. Do not vent gases into the atmosphere.

Refrigerant type:

R410A

GWP

(1)

 value:

1975

(1)

 GWP = global warming potential

The refrigerant quantity is indicated on the unit name plate.

Mounting the unit

1

Check the strength and level of the installation ground so that
the unit will not cause any operating vibration or noise after
installation.

2

Make sure that the unit is installed level.

3

Prepare 4 sets of M8 or M10 foundation bolts, nuts and washers
each (field supply).

4

Fix the unit securely by means of the foundation bolts in
accordance with the installation drawing.
Screw in the foundation bolts until their length remains 20 mm
above the foundation surface.

Drain work

If drain work is necessary, follow the guidelines below.

Two drain outlets are provided in the bottom plate of unit, see

"Unit installation drawing" on page 5

 (drain plug and drain hose

are field supply).

In cold areas, do not use a drain hose with the unit. Otherwise,
drain water may freeze and block the drain. In case the use of a
drain hose is unavoidable for one reason or another, it is
recommended to install a heater tape in order to protect drain
from freezing.

Water pipework

Checking the water circuit

The units have a water inlet and water outlet for connection to a water
circuit. This circuit must be provided by a licensed technician and
must comply with all relevant European and national regulations.

Before continuing the installation of the unit, beware of the following
points:

Two shut-off valves are delivered with the unit. To facilitate
service and maintenance, install one at the water inlet and one
at the water outlet of the unit.

When operating the unit in a low outdoor ambient
temperature, be sure to follow the instructions described
below.

Construct a large canopy.

Construct a pedestal.

Install the unit high enough off the ground 
to prevent burying in snow.

Service space

1

Fixation holes

2

Drain outlets (Ø18 mm)

3

Water inlet

4

Water outlet

580

137

69

367

1170

>50

330

360

350

>100

1

1

3
4

2

The unit is only to be used in a closed water system.
Application in an open water circuit can lead to excessive
corrosion of the water piping.

20

Summary of Contents for EWAQ005ACV3P

Page 1: ...INSTALLATION MANUAL EWAQ005ACV3P EWAQ006ACV3P EWAQ007ACV3P EWYQ005ACV3P EWYQ006ACV3P EWYQ007ACV3P Packaged air cooled water chillers and packaged reversible air to water heat pumps...

Page 2: ...acestea s fie utilizate n conformitate cu instruc iunile noastre 19 skladni z naslednjimi standardi in drugimi normativi pod pogojem da se uporabljajo v skladu z na imi navodili 20 on vastavuses j rg...

Page 3: ...t pump and cooling only versions This chiller range consists of two main versions a heat pump EWYQ version and a cooling only EWAQ version available in 3 standard sizes 5 kW 6 kW and 7 kW Heater tape...

Page 4: ...y operating the user interface When space cooling heating is requested by the room thermostat T the pump will start operating and the unit will switch to cooling mode heating mode The outdoor units wi...

Page 5: ...al power to the unit 3 Heat exchanger 4 Water inlet connection 1 MBSP 5 Water outlet connection 1 MBSP 6 Pump The pump circulates the water in the water circuit 7 Manometer The manometer allows readou...

Page 6: ...operation noise will not be amplified Although the noise produced by the unit during operation is low avoid installation near to places where even low noise levels can be disturbing e g bedroom windo...

Page 7: ...and level of the installation ground so that the unit will not cause any operating vibration or noise after installation 2 Make sure that the unit is installed level 3 Prepare 4 sets of M8 or M10 foun...

Page 8: ...r circuit The total water volume in the water circuit is 100 l In this example no action or adjustment is required Example 2 A heat pump model unit is installed 4 m below the highest point in the wate...

Page 9: ...filled with a weight concentration of glycol as mentioned in the table below Also refer to Checks before start up on page 11 Initial start up at low ambient temperatures Charging the water 1 Connect t...

Page 10: ...inal Protective earth 1 This wiring diagram only applies to the outdoor unit 4 Do not operate the unit by short circuiting protection devices Q1L S1L Field wiring guidelines The field wiring on the un...

Page 11: ...rminals on top of the front part of the digital controller and the terminals inside the unit P1 to 6 P2 to 7 4 Reattach the upper part of the digital controller First begin fitting from the clips at t...

Page 12: ...s available on the user interface UI or handled by the thermostat T space heating or cooling on off o heating cooling changeover heating and cooling schedule timers pr Heating cooling thermostat Remot...

Page 13: ...unit 7 Shut off valves Make sure that the shut off valves are correctly installed and fully open 8 Water pressure Make sure the unit is filled with water and that the water pressure is approximately...

Page 14: ...more than 5 seconds in normal mode s ba pfi and pfj Press these 4 buttons to switch to level 2 3 press again for 5 seconds to switch back to level 1 When level 2 3 is selected the actual permission l...

Page 15: ...9 00 Heating set point upper limit maximum leaving water temperature for heating operation 9 01 Heating set point lower limit minimum leaving water temperature for heating operation 9 02 Cooling set...

Page 16: ...carried out at regular intervals If the unit is used for air conditioning application the described checks must be executed at least once a year In case the unit is used for other applications the che...

Page 17: ...ere is sufficient water pressure The water pressure must be 0 3 bar water is cold 0 3 bar water is hot Check that the pump speed setting is on the highest speed III Make sure that the expansion vessel...

Page 18: ...or broken Contact your local Daikin dealer E1 A4P PCB defective in non accessible switch box Contact your local Daikin dealer E5 Overload activation of compressor Check that the unit is operating with...

Page 19: ...ormal 25 kPa high 40 kPa Sound level Sound power 63 dBA 64 dBA 66 dBA 63 dBA 64 dBA 66 dBA Sound pressure at 1 m distance 47 dBA 49 dBA 53 dBA 47 dBA 49 dBA 53 dBA Internal water volume 4 l Nominal wa...

Page 20: ...Zandvoordestraat 300 B 8400 Oostende Belgium 4PW33165 1D...

Reviews: