Test run and final check

The installer is obliged to verify correct operation of the unit after
installation.

Test run operation

1

Push the 

z

 button 4 times so that the 

t

 icon is displayed.

2

Depending on the unit model, heating operation, cooling
operation or both must be tested as follows (when no action is
performed, the digital controller will return to normal mode after
10 seconds or by pressing the 

z

 button once): 

To test the heating operation push the 

h

/

c

 button so the 

h

icon is displayed. To start the test run operation press the

o

 button.

To test the cooling operation push the 

h

/

c

 button so the 

c

icon is displayed. To start the test run operation press the

o

 button. 

3

The test run operation will end automatically after 30 minutes or
when reaching the set temperature. The test run operation can
be stopped manually by pressing the 

o

 button once. If there

are misconnections or malfunctions, an error code will be
displayed on the digital controller. Otherwise, the digital
controller will return to normal operation.

4

To resolve the error codes, see 

"Error codes" on page 16

.

Final check

Before handing over the unit to the user, read following
recommendations:

When the complete installation and all necessary settings have
been carried out, close all unit covers.

The service panel of the switch box may only be opened by a
licensed electrician for maintenance purposes.

M

AINTENANCE

In order to ensure optimal availability of the unit, a number of checks
and inspections on the unit and the field wiring have to be carried out
at regular intervals.

If the unit is used for air conditioning application, the described
checks must be executed at least once a year. In case the unit is
used for other applications, the checks must be executed every 4
months. 

 

Beware that some parts of the unit can be extremely hot. 

Chiller unit

1

Air heat exchanger

Remove dust and any other contaminant from the coil fins using
a brush and a blower. Blow from the inside of the unit. Take care
not to bend or damage the fins.

2

Fan motor 

Clean the cooling ribs of the motor.

Check on abnormal noises. If the fan or motor are damaged,
contact your local Daikin dealer.

3

Water pressure

Check if the water pressure is above 0.3 bar. If necessary add
water.

4

Water filter

Clean the water filter.

5

Water pressure relief valve

Check for correct operation of the pressure relief valve by
turning the red knob on the valve counter-clockwise:

If you do not hear a clacking sound, contact your local Daikin
dealer.

In case the water keeps running out of the unit, close both
the water inlet and oulet shut-off valves first and then contact
your local Daikin dealer.

Digital controller

The digital controller does not need maintenance.

Remove dirt with a soft damp cloth.

NOTE

Remark that during the first running period of the unit,
required power input may be higher than stated on the
nameplate of the unit. This phenomenon originates
from the compressor that needs elapse of a 50 hours
run in period before reaching smooth operation and
stable power consumption.

NOTE

To  display the last resolved error code, push the 

z

button 1 time. Push the 

z

  button again 4 times to

return to normal mode.

Before carrying out any maintenance or repair activity,
always switch off the circuit breaker on the supply panel,
remove the fuses or open the protection devices of the
unit. 

Do never clean the unit with water under pressure.

Summary of Contents for EWAQ005ACV3P

Page 1: ...INSTALLATION MANUAL EWAQ005ACV3P EWAQ006ACV3P EWAQ007ACV3P EWYQ005ACV3P EWYQ006ACV3P EWYQ007ACV3P Packaged air cooled water chillers and packaged reversible air to water heat pumps...

Page 2: ...acestea s fie utilizate n conformitate cu instruc iunile noastre 19 skladni z naslednjimi standardi in drugimi normativi pod pogojem da se uporabljajo v skladu z na imi navodili 20 on vastavuses j rg...

Page 3: ...t pump and cooling only versions This chiller range consists of two main versions a heat pump EWYQ version and a cooling only EWAQ version available in 3 standard sizes 5 kW 6 kW and 7 kW Heater tape...

Page 4: ...y operating the user interface When space cooling heating is requested by the room thermostat T the pump will start operating and the unit will switch to cooling mode heating mode The outdoor units wi...

Page 5: ...al power to the unit 3 Heat exchanger 4 Water inlet connection 1 MBSP 5 Water outlet connection 1 MBSP 6 Pump The pump circulates the water in the water circuit 7 Manometer The manometer allows readou...

Page 6: ...operation noise will not be amplified Although the noise produced by the unit during operation is low avoid installation near to places where even low noise levels can be disturbing e g bedroom windo...

Page 7: ...and level of the installation ground so that the unit will not cause any operating vibration or noise after installation 2 Make sure that the unit is installed level 3 Prepare 4 sets of M8 or M10 foun...

Page 8: ...r circuit The total water volume in the water circuit is 100 l In this example no action or adjustment is required Example 2 A heat pump model unit is installed 4 m below the highest point in the wate...

Page 9: ...filled with a weight concentration of glycol as mentioned in the table below Also refer to Checks before start up on page 11 Initial start up at low ambient temperatures Charging the water 1 Connect t...

Page 10: ...inal Protective earth 1 This wiring diagram only applies to the outdoor unit 4 Do not operate the unit by short circuiting protection devices Q1L S1L Field wiring guidelines The field wiring on the un...

Page 11: ...rminals on top of the front part of the digital controller and the terminals inside the unit P1 to 6 P2 to 7 4 Reattach the upper part of the digital controller First begin fitting from the clips at t...

Page 12: ...s available on the user interface UI or handled by the thermostat T space heating or cooling on off o heating cooling changeover heating and cooling schedule timers pr Heating cooling thermostat Remot...

Page 13: ...unit 7 Shut off valves Make sure that the shut off valves are correctly installed and fully open 8 Water pressure Make sure the unit is filled with water and that the water pressure is approximately...

Page 14: ...more than 5 seconds in normal mode s ba pfi and pfj Press these 4 buttons to switch to level 2 3 press again for 5 seconds to switch back to level 1 When level 2 3 is selected the actual permission l...

Page 15: ...9 00 Heating set point upper limit maximum leaving water temperature for heating operation 9 01 Heating set point lower limit minimum leaving water temperature for heating operation 9 02 Cooling set...

Page 16: ...carried out at regular intervals If the unit is used for air conditioning application the described checks must be executed at least once a year In case the unit is used for other applications the che...

Page 17: ...ere is sufficient water pressure The water pressure must be 0 3 bar water is cold 0 3 bar water is hot Check that the pump speed setting is on the highest speed III Make sure that the expansion vessel...

Page 18: ...or broken Contact your local Daikin dealer E1 A4P PCB defective in non accessible switch box Contact your local Daikin dealer E5 Overload activation of compressor Check that the unit is operating with...

Page 19: ...ormal 25 kPa high 40 kPa Sound level Sound power 63 dBA 64 dBA 66 dBA 63 dBA 64 dBA 66 dBA Sound pressure at 1 m distance 47 dBA 49 dBA 53 dBA 47 dBA 49 dBA 53 dBA Internal water volume 4 l Nominal wa...

Page 20: ...Zandvoordestraat 300 B 8400 Oostende Belgium 4PW33165 1D...

Reviews: