2.4 Instructions for operating safety
2.4.1 Working on the roof
●
Installation work on the roof may only be
carried out by authorised and trained persons
(heating technicians, roofers, etc.) in
compliance with the relevant Accident
Prevention Regulations.
●
Material and tools must be secured against
falling.
●
Barriers must be erected to prevent persons
from entering the area below the roof where
the work is being carried out.
2.4.2 Before working on the heating system
●
All work on the heating system (such as instal-
lation, connection and initial start-up) may
only be carried out by authorised and trained
heating technicians.
●
Switch off the main switch and secure it
against unintended switching on when
carrying out any work on the heating system.
2.4.3 Electrical installation
●
Electrical installations must only be carried
out by electrical engineers and in compliance
with valid electrical guidelines as well as the
specifications of the energy supply company
(EVU).
●
Connect the mains in accordance with
IEC 60335-1 via a separator device which
exhibits contact separation in all poles with a
contact opening distance that provides full
disconnection in accordance with the condi-
tions of overvoltage category III and a residual
current circuit breaker (RCD) with a reaction
time
≤
0.2 s.
●
Compare the mains voltage (230 V, 50 Hz)
indicated on the nameplate with the supply
voltage before connecting to the mains.
●
Before beginning work on live parts,
disconnect them from the power supply
(switch off main switch, remove fuse) and
secure against unintentional restart.
●
Equipment covers and service panels must be
replaced as soon as the work is completed.
2.4.4 Installation room, water quality, heating
and sanitary connection
The requirements on installing the hot water tank
(EKHWP or Altherma EHS(X/H)B), on the water
quality, as well as the heating and sanitary con-
nection are described in detail in the instructions
for the hot water tank. It is essential they are
complied with.
2.4.5 Instruct the owner
●
Before handing over the heating system,
explain to the user/owner how to operate and
check the heating system.
●
Document the handover by filling out the
installation and instruction forms together with
the owner and sign them.
2.4.6 Relevant national regulations
●
DIN 1055-4: 2005 / EN 1991-1-4 Wind actions
●
DIN 1055-5: 2005 / EN 1991-1-3 Snow loads
●
DIN 18338 Roofing work
●
DIN 18451 Scaffolding work
●
DGUV Information 208-016
●
DGUV Information 201-054
●
DGUV Regulation 112-198
The accident prevention regulations must be
heeded when working on the roof.