Startup and shutdown procedures
PRE-START-UP CHECKLIST
Date:
Place of Work:
Location:
Installing Contractor:
Technician/Company:
Unit Commissioning:
Unit model:
Serial number:
The following data should be checked before putting the unit into operation.
PHYSICAL INSPECTION (BEFORE ELECTRICAL CONNECTION)
Check that the unit has not been damaged by handling or transport.
Visually check for refrigerant leaks.
Open the unit for hydraulic installation only. Do not remove the connection guards until the hydraulic
circuit is closed.
Check for foreign objects in the fan discharge.
Check that the air inlet is not obstructed and has the suggested clearance.
INSPECTION OF THE HYDRAULIC CIRCUIT
Date:
Place of Work:
Location:
Installing Contractor:
Technician/Company:
Unit Commissioning:
Unit model:
Serial number:
NOTE: Accessories such as thermometers, pressure gauges, measuring ports, etc., are recommended but not necessary for
the operation of the unit. Are recommended but not necessary for the operation of the unit.
It is necessary to install a water filter in all hydraulic circuits to prevent the entry of solid particles, these must be installed on the return
side of the circuit and must be cleaned once the initial system load is finished.