D-EIMWC00908-16EN - 41/52
System maintenance
WARNING
All routine and extraordinary maintenance activities on the machine must be carried out only by qualified personnel who
are familiar with the machine characteristics, operation and maintenance procedures, and who are aware of the safety
requirements and risks involved.
WARNING
The causes of repeated shutdowns deriving from triggering of safety devices must be investigated and corrected.
Re-starting the unit after simply resetting the alarm can seriously damage the equipment.
WARNING
A correct refrigerant is essential for optimal operation of the unit and for environmental protection.
To protect the environment, do not release refrigerant into the atmosphere. Always use a recovery and storage device.
Any efrigerant recovery must conform to legislation in force.
General
IMPORTANT
Besides the checks suggested in the routine maintenance program, it is recommended to schedule periodical
inspections, to be carried out by qualified personnel, as follows:
4 inspections per year (1 every 3 months) for units running about 365 days per year;
2 inspections per year (1 at seasonal start-up and the second one in the middle of the season) for units running about
180 days per year with seasonal operation.
1 inspection per year for units that run for a season of approximately 90 days/year (at seasonal start-up).
It is important that during initial start-up and periodically during operation, routine verifications and checks are performed.
These must also include verification of evaporation and condensation pressure. Verify through operator interface panel
that the machine operates within the normal superheating and subcooling values. A recommended routine maintenance
programme is shown at the end of this chapter while a form for collecting operational data can be found at the end of this
manual. Weekly recording of all the machine’s operating parameters is recommended. Collecting this data will be very
useful to the technicians in the event that technical assistance is called for.
Compressor maintenance
IMPORTANT
Since the compressor is of the semi-hermetic type, it requires no scheduled maintenance. However, for granting the
highest levels of performance and efficiency and for preventing malfunctions, it is recommended that a visual check is
carried out at least every 10.000 running hours.
Such inspection has to be carried out by qualified and trained personnel.
The analysis of vibrations is a good method for verifying the mechanical conditions of the compressor.
Verification of vibration readings immediately after start-up and periodically on an annual basis is recommended. The
compressor load must be similar to the previous measurement’s load to ensure measurement reliability.
Summary of Contents for C10FZXS
Page 16: ...D EIMWC00908 16EN 16 52 Figure 4 Evaporator pressure drop...
Page 17: ...D EIMWC00908 16EN 17 52...
Page 18: ...D EIMWC00908 16EN 18 52 Figure 5 Condenser pressure drop...
Page 34: ...D EIMWC00908 16EN 34 52 Figure 12 Compressor overview...
Page 50: ...D EIMWC00908 16EN 50 52...