Part No. 4801-5120 Rev. 1-2020
Mega-Cool System
Page 18 of 48
Install Spray Line
1. Glue spray line sections together. Important! Glue joints with
spray line holes pointed in the same direction. Allow glue to
dry.
NOTE
: If a Center-Mount In-Line Pump System is being
installed, the spray line must have a tee joint in the
middle. Refer to the Center-Mount System Diagram on
Page 25. Spray line tee installation will be simplified if
the spray line is cut after the In-Line Pump & supply
line is plumbed and the correct tee placement verified.
2. Insert spray line assembly into one end of top bracket. Slide
assembly until spray line spans entire length of top bracket.
3. Rotate spray line to place holes facing upward for Closed
Spray Cover option. For Open Spray Cover option, adjust
holes after installing Spray Cover. See Page 18. (NOTE:
Side View shown at left).
Rotate spray line
To point holes
upward
Closed
Cover
Option
Open
Cover
Option
Rotate spray line
To point holes
at angled corner of
Cover
Spray Line Installed With Holes Upward
1
2
3
Assemble Spray Line
Lay Spray Line into Top Support Brackets
Top Support
Bracket
TOP VIEW
TOP VIEW
Be sure to point holes in the same
direction when gluing Spray line.