INSTALLATION STEPS
TEST FOR SPILLAGE
CHECK FOR SATISFACTORY CLEARANCE OF COMBUSTION PRODUCTS
CLOSE ALL DOORS AND WINDOWS IN THE ROOM CONTAINING THE FIRE
TURN ON GAS SUPPLY , LIGHT THE FIRE AND SET THE CONTROLS TO HIGH
LEAVE THE FIRE BURNING FOR FIVE MINUTES AND INSERT A LIGHTED SMOKE MATCH ON A
VERTICAL PLANE
20 mm DIRECTLY UNDER FRONT EDGE OF CANOPY AND 75mm FROM EITHER SIDE OF THE OPENING
(SEE DRAWING )
ALL THE SMOKE MUST BE DRAWN INTO THE FLUE.
IF SPILLAGE OCCURS ALLOW A FURTHER TEN MINUTES.
SHOULD SPILLAGE STILL OCCUR TURN OFF THE FIRE AND SEEK EXPERT ADVICE
IF AN EXTRACTOR FAN IS SITUATED IN THE ROOM THIS TEST SHOULD BE REPEATED WITH THE FAN
RUNNING
IF THERE IS A CONNECTED ROOM WITH AN EXTRACTOR FAN , THE TEST SHOULD BE REPEATED
WITH ALL THE DOORS TO THAT ROOM OPENED AND THE EXTRACTOR FAN RUNNING.
FIG 14
DIRECTLY UNDER FRONT EDGE OF CANOPY
20MM IN FROM CANOPY EDGE
75 mm from
side OF TRIM
ISSUE1