2.5.2 Power-On Settings
NOTE: THE LAST STATUS OF A UNIT IS RETAINED EVEN WHEN POWER IS REMOVED.
WHEN POWER IS RESTORED, THE UNIT WILL RETURN TO IT'S PREVIOUS SETTINGS.
When power is first applied, the LCD display goes through three steps.
1. The LCD goes black to show all segments are functioning.
2. The software version will be displayed.
2099-2424W28
4.0
3. The present LNB and SSPB inserted voltage and current are shown.
SSPB +24.1V @ 1.800A
LNB +24.2V @ 0.27A
The unit is now operational and ready for any changes the operator may desire.
2.5.3 Control Switches
1. Menu/Execute - Any change to the programming of the unit must be initiated by pressing the
Menu/Execute switch and completed by pressing the Menu/Execute switch.
2. Horizontal Switch - This switch is mounted so its movement is horizontal and moves the cursor left or
right.
3. Vertical Switch - This switch is mounted so its movement is vertical and will toggle settings such as
ON/OFF and RS232/422/485. In the case of the LEVEL setting, the vertical switch will increase or
decrease the digit that is selected (within the limits of operation).