SCF-6 Canister and Inline Splice Closures
KPA-0493
Refer to SRP 206-286 (Mechanical End Cap Canister Closure Sealing Checklist) to ensure all
critical
steps in Section 5.14 and 5.15 for sealing the closure have been performed accurately.
5.17
Reenter the Inline Closure
Step 1
If it is necessary to reenter the inline closure, verify there is no pressure by
removing external ground screw and allowing air to escape.
Step 2
Remove clamping bars. Pry upwards with a flat-tip screwdriver to open the
clamping bar locks (Figure 60). Alternately tap against the stop on the top of the
bars (Figure 61).
KPA-0494
Step 3
Perform any tests, modifications, or examinations of the closure that are necessary.
Step 4
Reinstall the clamping bars per Section 5.12.3.
Step 5
Flash test closure per Section 5.14 on every entry.
Step 6
Reterminate ground, if applicable, per Section 5.15.
5.18
Reenter the Canister Closure
Step 1
If it is necessary to reenter the canister closure, verify there is no pressure by
removing external ground screw and allowing air to escape.
Step 2
Remove clamping ring by untightening the two bolts.
Step 3
Perform any tests, modifications or examinations of the closure that are necessary.
Step 4
Reinstall the clamping ring per Section 5.13.2.
Step 5
Flash test closure per Section 5.14 on every entry.
Step 6
Reterminate ground, if applicable, per Section 5.15.
Figure 60 — Pry Locks Open
Figure 61 — Hammer Clamping Bars Off