Installation Instruction
Figure 3
Figure 5
Figure 6
Figure 7
5.1.3 To connect several rails together, slide
half of the splice into the rear side of the
rail. Fasten the first M8 Bolt using an Allen
key, and slide the next rail into the splice as
shown in Figure 3. Tighten the second M8
Bolt using an Allen key. The total rail length
is recommended not to be over 30 meters
considering rails thermal expansion problem.
M8 Bolt Recommended torque is 10 ~12 N·m.
Splice provides the electrical connection
between the 2 rails through the pressure
bolts. This eliminates the need of using 2
earthing lugs In case of large purlin spacing,
MT-Rail Support with T50 or T110 Rail will be
an option. Please follow the steps below.
In case of large purlin spacing, MT-Rail
Support with T50 or T110 Rail will be an
option. Please follow the steps below.
5.2.1 Based on the rib spacing of metal roof
sheet, mark out the positions of self-tapping
screws (Clenergy 240 mm long MT rail
section is equipped with two Buildex 14-11
x 70 Hex Head Zips screws) on the MT-Rail
Support and then attach the glued EPDM
rubber pad under the MT–Rail Support as
shown in Figure 4.
5.2.2 Confirm the position of the purlin for the
MT-Rail Support installation, then fix the MT-
Rail Support through two ribs on the purlin as
shown in Figure 5.
5.2.3 Fix the Rail onto the MT-Rail Support
with T-Rail Clamps as shown in Figure 6 and
7.
Figure 4
5.2 MT-Rail Support with T50/T110 Rail Installation (optional)