INSTALL OPTIONAL SIDE PANELS
Side panels are attached to the sidewall frame and
ground posts and help to shield the interior from weather
and wind. Side panels can be installed to decrease
distractions, or removed to increase ventilation and light.
ATTENTION:
Skip this procedure if you are not installing
side panels at this time.
Parts required for the side panel installation.
•
Side Panels
•
Tie-Downs
Complete the following steps to install the side panels.
Photo shows side panels on a similar shelter.
1. Unfold a side panel and position it between two
ground posts.
2. Insert the end of the tie-down through the grommet
of the side panel.
Diagram shows a snugger ball tie down.
3. Wrap the tie-down cord around the ground post or
frame tube and thread the ball of the tie-down
through the double cord of the tie-down to secure it
in place. See previous diagram.
Photo may show a shelter that differs in design.
Photo is used to show the position of the tie-downs and
the side panels. Shelter shown may differ from your
shelter.
4. Repeat the steps to install the remaining tie-downs
for the panel.
5. Repeat the procedure to install the remaining side
panels.
6. Read
the
High Crown Arena Care and
Maintenance
information.
Visit www.ClearSpan.com for additional products and customer assistance.
24 of 36