25
B.2 Rack mounting work flow
TABLE B.1 Rack mounting work flow
sequence
Work item
1
Confirming the components of the rail kit
2
Confirming rail mount position
3
Mounting the right side rail
4
Mounting the binder
5
Mounting the left side rail
6
Mounting the binder
7
Mounting the C880 M4 cabinet in the rack
8
Securing the C880 M4 cabinet with screws
B.3 Confirming the components of the rail kit
TABLE B.2 shows components of the rail kit.
Please confirm the components.
TABLE B.2 Components of the rail kit
Name
Drawing No.
Qty
Remarks
RAIL LEFT
SNP:A3C40122926
1
See Figure B.2
RAIL RIGTH
SNP:A3C40124429
1
BINDER
SNP:A3C40108821
2
M5 screw with plug washer
SNP:A3C40063207
6
CENTERING SCREW
SNP:A3C40121631
10
CAGE NUT
SNP:0007000120
4
FIGURE B.2 Components of the rail kit