39
G
Verification
Once the entire installation procedure is completed, check the following points:
•
Check that all the MCB, RCD and the Main Circuit Breaker are powered on.
•
Check that all safety labels are placed correctly.
•
Close the Charge Point’s doors. The Charge Point has a security switch (anti-
tamper protection) installed that will avoid any charging session if the doors are
opened.
•
Check that all beacons are illuminated in green.
•
Verify that each EV connector is in good condition.
•
Make sure the ventilation air flow is correct and there is not any obstruction at
the ventilation grill. EVSE activates the Power module fan when charging and the
roof fan when temperature is above the limit. This is managed by Mode 4 control
board.
•
Check for abnormal noise while charging a vehicle.
Summary of Contents for CCS CHA T2C63
Page 1: ...Installation Manual Raption Series ...
Page 2: ......
Page 4: ......
Page 7: ...03 ...
Page 17: ...13 ...
Page 18: ...14 Raption Series Installation Manual 3 A Dimensions Units specified in milimeters ...
Page 53: ...49 ...