2.13 INSTRUCTIONS FOR ADDING A SALT FEED RELAY
Mount the salt feed relay box to the wall close enough to the power supply so that the patch
cord will connect to the FEED SALT connector on the power supply. Plug the relay box into a
120 VAC outlet. Plug the peristaltic pump used for feeding salt into the output plug on the
relay box.
2.14 ELECTROLYTIC CELL WIRING
Connect the red connector from the power supply to the red connector at the cell.
NOTE:
Never remove the cables from the top of the cell. Always disconnect the cell with the
red connector.
2.15 BONDING THE SYSTEM
All ChlorKing® systems include cell-bonding assemblies. These assemblies are included in
the install kit. The bonding assemblies must be connected with a minimum of 8 AWG bonding
wire. Connect the bonding wire from the top cell grounding assembly to the bottom cell
grounding assembly and then from the bottom cell grounding assembly to the bonding lug
located on the outside of the power supply. The bonding lugs on the power supply are clearly
marked with a decal that reads “Bonding Lugs”. Connect the second bonding lug on the power
supply to the bonding grid at the facility.