Operating the Device
15
Chloride Linear Plus Series Rack-mount UPS User Instruction Manual
6. Close any external switches connecting the load (if present).
7. Press the button
on the UPS control panel for a minimum of 1 second to switch on the inverter
(see “Control Panel for the Linear Plus Rack-mount” on page 16).
In addition to the “LINE” and “BYPASS” LEDs the “LOAD” LED and “BATTERY” LED is now
illuminated. After a few seconds the “INVERTER” LED is illuminated and the “BYPASS” LED is
extinguished. The UPS is now in ON-LINE operation.
UPS Shutdown
Procedure
NOTE: Carrying out this procedure will interrupt the supply to the load.
1. Press the button
on the UPS control panel for a minimum of 1 second to switch off the inverter.
2. Open any external switches connecting the load (if present).
3. Switch input breaker to position (0) OFF.
4. Switch off the battery breaker. to the open (O) position.
5. Ensure all mains switches and circuit breakers upstream of the UPS are open.
6. Ensure that all LEDs on the control panel are extinguished. The UPS is now completely shutdown.
Functional Test
NOTE: Supply to the load is not guaranteed during this test, it should not be carried out if a critical load
is connected to the UPS.
It is possible to carry out a functional test of the UPS to ensure that the load is still supplied in the event
of a mains failure.
Simulate a mains failure by interrupting the mains supply to the UPS. If the UPS is operating correctly
and the batteries are fully charged, an acoustic signal at intervals of 4 seconds will be heard and the “ON”
LED indication “MAINS “indicator (6) at the UPS will be extinguished. Once the interval between the
acoustic signals has decreased to 1 second, the UPS will continue to supply energy for a maximum of 3
more minutes, after which it will be automatically switched off.
The load will be supplied from the batteries during the specified emergency supply period. If this is not
the case, please consult chapter “Troubleshooting” on page 25”.
Restore the UPS mains supply. The UPS is ready for operation. Please note, that the batteries have to be
recharged before the complete emergency supply period is again available.
NOTE: The unit indicates an alarm condition, when the battery is not connected.
Canceling the battery alarm
1. To cancel the alarm, connect the battery and close the battery breaker.
2. Switch the unit to online mode by pushing the button
.
The unit checks the battery voltage (a beep is heard) once more and stays in bypass till a constant battery
voltage is present.
Battery maintenance must be carried out by authorized personnel observing the necessary precautions.
Parallel operation
Please refer to chapter “Paralleling UPS Devices” on page 19
Indication and
Operating Elements
Linear Plus
Rack-mount
NOTE: To effect any action, the buttons must be pressed for at least 1 second! (Acceptance of the input
is confirmed acoustically)
The following is an explanation of the symbols printed on the front panel of the UPS:
Summary of Contents for LP061XHR
Page 1: ......
Page 3: ......
Page 5: ......
Page 33: ...Troubleshooting Chloride Linear Plus Series Rack mount UPS User Instruction Manual 28 ...