56 

 

9.3.4 History 

Click “History” to enter a history menu. There are 3 submenus under this menu, including “Fault 
Record”, “Power Curve” and “Electric Energy Production Curve”. 
(1)  Under  the  “Fault  Record”  menu,  4000  recent  faults  together  with  fault  occurrence  and 

clearance  time  records  can be  seen;  it  can  support  page  turning  check  and  page  skipping  check. 

Format of fault record: 

No. 

Time 

State 

Fault 

16-02-01 16:41:15 

Clearance 

Module 

Over-temperature 

protection 

16-02-01 16:35:02 

Occurrence 

Module 

Over-temperature 

protection 

The above record shows that “Over-temperature protection” fault happens to Module 1 at 16:35:02 

Feb. 1st, 2016, and is cleared at 16:41:15 Feb. 1st, 2016. If complete machine fault happens, the 

number of module will not be displayed. 
(2) Under the “Power Curve” menu, the power curve on the same day is checked. 
(3) Under the “Electric Energy Production Curve” menu, one can see the bar graph of total electric 

energy  production per year  and monthly  total electric energy  production  per  year  in  the past  ten 

years together with the bar graph of daily electric energy production per month in the same year. 

 

9.3.5 Inverter parameter  

Click “Inverter Parameter”, pop out the textbox of password port to input passwords (Contact our 

after-sales  service  center  to  acquire  the  passwords),  and  click  “Enter”  key  to  enter  an  inverter 
parameter  setting  interface.  The  menu  comprises  3  submenus:  “Protection  Parameter”,  “Rule 
Selection” and “Command Parameter”. 

(1)Switching between the complete machine and all modules 
After it enters the “Inverter Parameter” menu, the interface as shown in the following figure can 

be seen: 

 

Figure 9-4 Protection parameters 

CPS SCH1500K inverter is provided with 2 modules altogether; switching between the complete 
machine  and  all  modules  can  be  achieved  by  clicking  “System”  button,  “Module  1”  button, 
“Module  2”  button  and  other  buttons  so  that  protection  parameters  of  all  the  modules  can  be 

110.0 

2.00 
90 

135.0 

0.05 

50.0 

0.10 

108.0 

92.0 

5.00 

4.0 

2016-02-05 14:04:30 FRI 

Summary of Contents for CPS PSW1.5M-1500V

Page 1: ...CPS PSW1 5 3M 1500V Inverter Container User Manual ...

Page 2: ...rotection 10 2 2 6 Live Line Measurement 10 2 2 7 Measuring Instrument 10 2 2 8 Volt free Operations 10 2 2 9 ESD Protection 10 2 2 10 LCD Parameter Setting 11 2 2 11 Sand and Moisture Protection 11 2 2 12 Symbols on the Device Body 11 2 2 13 Safety Warning Signs 11 2 2 14 Daily Operation and Maintenance 11 2 2 15 Disposal of Waste 12 2 2 16 Manual Description 12 3 Product Description 13 3 1 Conta...

Page 3: ...Site 24 5 4 2 Foundation Requirements 25 5 4 3 Recommended foundation construction method 25 5 4 4 Other Precautions 28 5 5 Fixing the Container 28 5 6 Flashings Installation 28 5 6 1 Brief Introduction 28 5 6 2 Installation Steps 29 6 Electrical Installation 30 6 1 Safety Instructions 30 6 2 Parts for Cabling 31 6 2 1 Copper Wire Connection 32 6 2 2 Aluminum Wire Connection 32 6 3 Preparation bef...

Page 4: ...4 7 1 Safety Instructions 44 7 2 Requirements of Commissioning 44 7 3 Checking before Commissioning 45 7 3 1 Checking the Cable Connection 45 7 3 2 Checking the Inverter 45 7 3 3 Checking PV Array 45 7 3 4 Checking Grid Voltage 46 7 4 Preparation before Starting 46 7 5 Starting the Device 46 7 6 LCD Parameter Setting 47 7 7 Completing Commissioning 47 8 Operation 48 8 1 Check before start up 48 8 ...

Page 5: ... Troubleshooting 66 11 1 Safety Instructions 66 11 2 Fault Checking 66 11 3 Fault and Troubleshooting on the LCD screen 67 12 Routine Maintenance 75 12 1 Safety Instructions 75 12 1 1 Safety Instructions 75 12 1 2 Five Safety Rules 75 12 2 Maintenance 76 12 2 1 Introduction 76 12 2 2 Maintenance Interval 76 12 2 3 Container filter checking and cleaning 79 12 2 4 Inverter air filter cleaning and re...

Page 6: ...op the container internal devices during normal operation User interface Function and use of the container HMI Functions Descriptions of the container main functions Troubleshooting Simple troubleshooting of the container Daily operation Instructions and guide of the daily operation of the container 1 4 Target Group This manual is for technical personnel who are responsible for the transport insta...

Page 7: ...which if not avoided could result in equipment or property damage NOTE NOTE indicates additional information emphasized contents or tips to help you solve problems or save time The symbols below may be pasted on the electrical parts of the container Make sure to read the following symbols and fully understand them before installing the equipment Symbol Explanation Lethal voltage inside Do not touc...

Page 8: ...are changes of manual in the subsequent inverter edition The latest manual can be acquired via visiting the web site at www chintpower com 1 7 Terminology In this manual the inverter container will be referred to as container and the central PV grid connected inverter will be referred to as inverter unless otherwise specified ...

Page 9: ...hown in the following figure A B C D E Figure 2 1 Application of Container to the PV Power System No Name A PV Array B PV Array Combiner Box C Container D Transformer E Utility Grid WARNING Installation of the container not in compliance with the description in this manual or installation or modification of the device without authorization from CPS may lead to personal injuries or device damages a...

Page 10: ...related items must be complied with Please read all the instructions thoroughly prior to any operation work on the container Transport install maintain and service the container by strictly following the descriptions in this manual Device damage personal injury or property loss may follow if otherwise This manual and relevant documents should be available for relevant persons at all times 2 2 3 Em...

Page 11: ...igh quality instrument with sufficient measuring range Make sure the connection and use of the instrument are correct to avoid arc and other dangerous situations Use suitable protective equipment for example dielectric gloves if live line measurement is required 2 2 8 Volt free Operations Perform operations on the container only when all devices inside the container esp the inverter are completely...

Page 12: ...on maintenance and troubleshooting of the container keep non related persons away Post warning signs near the container upstream and downstream switches to prevent accidental connection Place necessary warning signs or barriers near the on site operation areas 2 2 14 Daily Operation and Maintenance Make sure the container doors are closed and locked during daily operation to prevent internal devic...

Page 13: ...sed of together with household wastes Some components inside can be recycling and some components can cause environment pollution Please contact the local authorized collection point 2 2 16 Manual Description NOTE For user s convenience there are a large number of pictures in this manual These pictures are indicative only For details about the device please refer to the actual product you receive ...

Page 14: ... Front of the container a single door is equipped the container external grounding point is located on the lower left side Back view Back of the container the container external grounding point is located on the lower left side Danger Danger Left view Left of the container an equipment door is equipped ...

Page 15: ...er External dimensions without the flashings are shown in figure below Left view Front view Danger Danger Danger Figure 3 1 Appearance and dimensions of the container Width Height Depth Weight 2991mm 2591mm 2438mm Approx 5000kg with internal devices 3 1 3 Internal Components Figure below shows the top view of the major electrical components inside the container Container front view Figure 3 2 Cont...

Page 16: ... ventilation system is designed as cool air coming inside from the bottom of the container and hot air getting outside the container from the top of the container Hot air emitted by the inverters and hot air of the container internal cooling fans is extracted out of the container through the air ducts on top of the container Air out in the following figure Danger Danger Danger 1MW PV Power Station...

Page 17: ...on cables go inside the container through this hole 3 1 6 Flashings Design Flashings should be installed to all the 5 air outlets on the left back and right of the container Under the flashings are anti dust filters The design and installation of the flashings can greatly reduce the effect of rain and wind and sand to the ventilation ducts Remove the cover plates and install the corresponding flas...

Page 18: ... to perform the electrical connection work A B C Figure 3 7 Electrical connections area of the inverter Item Descriptions Markings on the Device A DC connection areas DC DC Inverter supports up to 12 DC inputs B AC connection area L1 L2 L3 C Ground terminal 3 3 Power Distribution Box Design The power distribution box integrates the function of power distribution The power distribution function int...

Page 19: ...integrated communication function the inverters signals and temperature humidity controller signals can be output from the distribution box to the outside NOTE Please confirm the configure of the power distribution box according to the project requirement Please refer to the actual filed configuration ...

Page 20: ...PS 1MW PV Power Station Shanghai Chint Power Systems Co Ltd Danger Danger xx MW PV Power Station Model Name Max DC Input Power SHANGHAI CHINT POWER SYSTEMS CO LTD Rated AC Output Power Max DC Input Voltage Max DC Input Current MPPT Voltage Range Protection Class Max AC Output Current Rated Output Frequency Max Efficiency Protection Degree Dimension Weight Rated AC Output Voltage Euro Efficiency Ma...

Page 21: ...Check to make sure the container and inner devices are the models placed in your order Check thoroughly the container and inner devices for any possible damages during transport WARNING Install and commission the container only when it is technically faultless Make sure before installing the container that Container is intact without any damage All devices inside the container are intact without a...

Page 22: ...epth 2991mm 2591mm 2438mm Weight approx 5000kg Ensure that the following requirements are met All the doors are locked Choose appropriate crane or hoist to transport the container The crane or hoist must be sufficient to bear the weight of the container An additional traction vehicle may be needed when the road has a gradient Anything which may hinder the transport like trees cables or similar sho...

Page 23: ...sure the hoisting safety The following figure illustrates the hoisting operations Circle A describes the work areas of the crane Anybody standing inside the circle B is forbidden for safety considerations A B Station Station Crane Figure 5 1 Hoisting the Container 5 2 2 Hoisting In the whole hoisting process please observe following rules Hoist the container in a vertical manner Do not drag or dro...

Page 24: ...ould be tightened WARNING National and local safety rules should be observed at all times Regardless of relevant safety rules may void pertinent warranty claims from CPS 5 3 Transport with Forklift If the installation site is flat forklifts can be used to transport the container Standard fork pockets are designed at the bottom of the container for handling with forklifts During transport the fork ...

Page 25: ...pockets must be used to handle the container Under no circumstance should the container be handled by directly inserting the prong below the bottom of the container NOTE The slots and the container interior have already been sealed properly There is no need to seal the slots after the field installation 5 4 Foundation 5 4 1 Selection of Installation Site When selecting the installation site consid...

Page 26: ...rm enough The foundation should be at least 300mm higher than the ground level on site to avoid the rain damaging the base or the inside of the container Sufficient cross sectional area and depth of the foundation should be maintained The depth is designed according to local soil conditions Cable route should be taken into account NOTE According to the cable design of container and for easy electr...

Page 27: ...26 Container front view 1 2 ...

Page 28: ... hot galvanized steel plates diagonally at the foundation as the grounding units The recommended depth is 0 8m Weld one end of the hot galvanized steel plates with the main grounding network of the power container and the other end with the pre buried steel plates Make sure the welding is firm and reliable It is recommended to build steps at the front door of the container to facilitate entry of p...

Page 29: ...heck to ensure that the foundation construction has met all the local standards and other relevant requirements Hoist the container onto the foundation after the foundation is dry enough Container front view Figure 5 5 Hoisting position Weld the container base with the 4 pre buried steel plates by using 6 steel angles Anti rust treatment for the container and foundation should also be done 5 6 Fla...

Page 30: ... be able to withstand temperature of at least 70 5 6 2 Installation Steps Proceed as follows to install the flashing Step Figure Description 1 Remove the sealing plate Remove the sealing plate before installing the flashing Unscrew the fastening screws around the plate to remove the plate 2 Figure in the left is the view after the plate is removed 3 Install the flashing Install the flashing to the...

Page 31: ...on from the local network operator WARNING Only professional electricians can perform the operations described in this chapter Observe all the instructions to connect the wires WARNING Disconnect all AC and DC Switches before electrical connection WARNING Sand and moisture penetration may affect the performance of electric devices inside the container Do not perform electrical connection in sandy ...

Page 32: ...es when necessary WARNING Strictly follow all the instructions when connecting the cables NOTICE The installation and design of the container must fulfill national and local standards and regulations CPS should hold no liability for the container or system fault caused by ignorance of the description in this manual Five Safety Rules During electrical connections and other operations on the inverte...

Page 33: ...delivery Please respect the description in this chapter during connection 6 2 1 Copper Wire Connection If copper wires are used connect the spare parts as described below Figure 6 1 Copper wire terminal connection sequence A B C D E F Copper Bus Cable Lug Bolt Spring washer Flat washer Nut 6 2 2 Aluminum Wire Connection When the aluminum wire is selected a copper aluminum bi metallic lug is needed...

Page 34: ...ore installation Torque wrench Screwdriver Wire stripper Terminal crimping device Alcohol blast burner or hot air blower Allen wrench Meg ohmmeter or multimeter Other auxiliary tools or spare parts 6 3 2 Opening the Inverter Front Door Before electrical connection user needs to open the inverter front door Cabinet door keys are needed to open or close the front door Proceed as follows to open the ...

Page 35: ...erter through the bottom of the inverter Proceed as follows to open the cable entries Step 1 Turn the two nuts on the back of the cover plate counterclockwise until the cover plate can move forward and backward Step 2 Turn the cover plate backward to open the cable entries NOTICE The protective sponges are used to protect the cable from scratches Do not remove them 6 3 5 Checking the Cables WARNIN...

Page 36: ...485 Ethernet Ethernet C C Communication circuit 1 Communication circuit 2 3 3 K A A B D E 2 1 Optional 3 3 K A A B D E 2 1 Optional RS485 RS485 C RS485 Ethernet Ethernet C C Communication circuit 3 Communication circuit 4 Figure 6 4 Container main circuit diagram Devices in the above figure are Item Name 1 2 Inverter 1 inverter 2 K Power distribution box ...

Page 37: ...luminum armored cable or 120 240 mm2 copper armored cable for each output C Inverters communication interface RS485 and Ethernet interface for standard version D Multi function meter communication interface RS485 interface for standard version E Optional External 1 phase or 3 pahse container power supply Connect to container power supply to supply power to devices inside the container Recommend 10...

Page 38: ... of the whole plant using a grounding cable recommend 70mm2 copper cable on site External grounding Perform the external grounding according to the on site situation and the instructions of the plant staff The grounding resistance should be no more than 4Ω NOTE At least one of two points of the container external grounding must be connected to ground system of whole plant 6 6 AC Connection 6 6 1 S...

Page 39: ...longer than the depth of the cable lug Use DT xx xx is the cable cross sectional area copper lug based on the cable specification Step 4 Crimp the copper cable lug Put the stripped cables inside the cable lug Tighten the cable lug with proper tools The crimping number should be more than two Step 5 Install the heat shrinkable tubing Select tubing with dimensions matching with the cables Tubing len...

Page 40: ...pen circuit voltage is within the max DC voltage of the inverter Mark the negative and positive polarity of the cable Check the PV modules for possible ground fault WARNING Open circuit voltage of the PV array should not exceed the max DC voltage of the inverter The inverter may be damaged if otherwise If the ground fault is found it must be removed before any DC connection WARNING Strictly follow...

Page 41: ...lower NOTE Cable protectors are advisable in the cable crosses if the multi core cables are used Step 5 Connect the cable Select bolts matching with the cable lug recommend M10 Attach the cable lug to the DC connection copper bar following the sequence in the following figure Fasten the bolts with screwdriver or spanner with torque of 25N m WARNING Incorrect connection sequence may cause fire Plea...

Page 42: ...pper bars are shown as in Figure 6 9 Figure 6 9 Location of DC input connection 6 8 Auxiliary power and dry contact connection The auxiliary power supply of the inverter and the dry contact wiring position are located on the lower part of the right cabinet as shown in the following Figure 6 10 NOTICE DC power distribution circuit breakers are arranged from top to bottom with each column as one gro...

Page 43: ...dry contact to give alarms to the fault of the inverter Inverter external power supply and internal power supply through the switch selection ON on the left refers to the internal power supply the right side of the ON refers to the external power supply OFF refers to power Figure 6 11 Auxiliary power switch ON on the left refers to the internal power supply the right side of the ON refers to the e...

Page 44: ... is consistent with that in the groove NOTE The communication connection point may be located in the inverter may also be located in the power supply box so according to the actual receipt of the product to complete the communication connection 6 10 External 1phase or 3 phase Container Power Supply Optional If there is external power supply connected please connect the external power supply to the...

Page 45: ...no spare parts or tools are left inside the device NOTICE Close the doors of the container and the internal devices if the commissioning process is stopped 7 2 Requirements of Commissioning Before commissioning installation of the two inverters and the power distribution cabinet inside the container should be checked thoroughly Ensure all the cable connections are secure and all bolts are fixed pr...

Page 46: ...itches upstream and downstream meet the requirements and flexible enough 7 3 3 Checking PV Array WARNING Ensure the measuring devices are connected and used correctly Otherwise there will be electric arc WARNING DC side voltage should be no more than the inverter max input DC voltage Too high DC voltage may damage the inverter even cause safety incident NOTE To ensure the system reliability and de...

Page 47: ...the disassembled protection grills to their original positions and ensure the connection is secure Close and lock the cabinet door Clean the device site Make sure the position is clean without flammable or explosive materials Ensure the ventilation of the installation place Recheck and ensure inverter and switches upstream and downstream meet the requirements and flexible enough 7 5 Starting the D...

Page 48: ...ve been performed check the operating condition of the container Check whether there are anomalies of the inverter abnormal noise overheating smoking or unusual odor Check the inverter grid connected voltage current and THD for unstableness Check the grounding of the inverter enclosure Check the functionality of the LCD display Record accurately the inverter operation data during commissioning The...

Page 49: ...upply micro off to ON position 3 Make sure that the number of on line modules of the inverter is correct using the method given in the 9 3 2 Operation Information 4 Turn on the circuit breaker of one PV string in the combiner box 5 Turn on the DC circuit breaker of the inverter and close the front door of the inverter properly After the above operations are completed the inverter will automaticall...

Page 50: ...r will turn from standby to fault mode 4 Fault mode The inverter will disconnect from the power grid and turn into fault mode when the inverter or power grid fails Check the fault information on the LCD and find the specific cause and solution 8 4 Shutdown a Automatic shutdown When the PV panel output voltage and output power are lower than the NOTE CHINT is the reserved customized grid regulation...

Page 51: ...ds to enter the inverter parameter setting interface click Command Parameter Startup button to start the inverter Then the inverter will start up and operate normally if the start up condition is met Otherwise the inverter stands by c Maintenance shut down If the service personnel need to repair the inverter please shut down the inverter by LCD operations and then discharge the energy in the equip...

Page 52: ...ode The CPS SCH1500K adopts advanced digital control to realize high efficiency and high reliability of the inverter When sunlight is very weak the inverter is disconnected from the power grid until the voltage of the PV array is stably higher than start up voltage 8 6 Fault shutdown When the PV power generation system fails such as output short circuit grid overvoltage undervoltage grid overfrequ...

Page 53: ...res such as DC overvoltage overcurrent DC input reverse connection or 3 phase output AC interruption when the internal power mode is selected or external connection 220VAC interruption if auxiliary powering mode is selected If service personnel need to maintain the inverter please refer to Maintenance Shutdown After external troubleshooting is completed refer to the first power transmission proces...

Page 54: ... 9 1 indicates the definitions of LED lights i e the inverter s operation status When POWER lights up it indicates that the system is energized and under DSP control RUN will light up when the inverter detects that the grid connection meet the requirement and power is fed to the grid RUN will blink if the grid is in derated running state during the period of feeding power to the grid GRID will lig...

Page 55: ...Home page is a default interface as shown in Figure 9 2 The interface mainly displays daily power curve daily energy production active power CO2 emission reduction the number of DC inputs PV voltage PV current AC voltage AC current running mode current time and warning buzzer enabled mark Present fault alarm can be displayed at the bottom in a scrolling mode if it occurs Figure 9 2 Home page Click...

Page 56: ...ned when fault happens in the whole operation process of the inverter the present fault which does not disappear can display under the menu except sound light alarm Click Present Fault to check present fault information which supports page turning check Format of fault record No Time Fault 1 16 02 01 16 35 02 Module 1 Over temperature protection The above record shows that Over temperature protect...

Page 57: ...ar graph of total electric energy production per year and monthly total electric energy production per year in the past ten years together with the bar graph of daily electric energy production per month in the same year 9 3 5 Inverter parameter Click Inverter Parameter pop out the textbox of password port to input passwords Contact our after sales service center to acquire the passwords and click...

Page 58: ...on find the parameters to be changed then click and modify the parameter values and then click on the Enter key The protection parameters and the values that can be set are as shown in the following table Grid voltage protection parameters Protection parameters Default Max Min Upper limit of Class I grid voltage 110 0 135 0 100 0 Protection time for upper limit of Class I grid voltage s 5 00 655 3...

Page 59: ...or upper limit of Level II grid frequency s 0 20 1310 68 0 Lower limit of Level II grid frequency Hz 46 00 50 00 45 00 Protection time for lower limit of Level II grid frequency s 0 20 1310 68 0 Power grid overfrequency recovery point Hz 50 10 55 00 50 00 Power grid underfrequency recovery point Hz 49 60 50 00 45 00 Recovery time for abnormal grid frequency s 150 00 1310 68 0 Boot protection param...

Page 60: ...0 0 110 0 0 0 PF P curve PF2 0 9 1 00 1 00 PF P curve trigger voltage 90 0 110 0 80 0 PF P curve revocation voltage 80 0 110 0 0 0 SVG control 0 1 0 SVG reactive power 0 0 60 60 Reactive power control II Default Max Min QU curve U1 108 0 110 0 100 0 QU curve Q1 0 0 100 0 100 0 QU curve U2 110 0 110 0 100 0 QU curve Q2 50 0 100 0 100 0 QU curve U1i 92 0 100 0 90 0 QU curve Q1i 0 0 100 0 100 0 QU cu...

Page 61: ...y points and when the power grid undervoltage recovery points of the modules become consistent the red dot will disappear 3 Standard Selection menu to view and change the regulations In the Standard Selection menu the user can set and change the inverter grid connection regulations Figure 9 6 Standard selection 4 Order Parameters menu NOTICE Inconsistent settings of module protection parameters wi...

Page 62: ... needed the user can start the inverter through this menu to realize forced restart once Please note that this function is only available in case of failure and the inverter can restore itself in case of alarm failure and protection failure When the inverter is in the operation mode no response will be made to this function and the Illegal Operation warning will pop up Fast Discharge is only allow...

Page 63: ...ation of the system these dry nodes are used for connecting the passive signal contacts with the input signal being normally open or normally closed Supported alarm signals are inverter trip MW container over temperature trip MW container over temperature alarm MW container smoke alarm trip MW container access control alarm MW container fan failure distribution box surge failure distribution box m...

Page 64: ... the equipment and the contact information of the manufacturer are listed DSP Upgrade MCU Upgrade Export Data buttons are used for the manufacturer to update the inverter software and the users are not allowed to operate Click on the text area of the Software version to check the list of module software versions as shown in Figure 9 11 Figure 9 11 Version information 1 01 1 02 1 02 3338368712704 2...

Page 65: ...power Q Remote dispatching mode to remotely adjust the active dispatching reactive dispatching and power factor parameters via the monitoring software for details please refer to the user manual of the communication management unit or the user manual of the monitoring device NOTICE The user should contact the after sales service personnel before field debugging when using the power dispatching fun...

Page 66: ...is detected detector will issue a local audible or visual alarm and a warning signal The installation of smoke detector can protect the electrical devices and maintainers and operators The warning signal can connect to the fire alarm system of the PV system directly 10 2 3 Fire Emergency Lights Fire emergency lights an external power supply backed lighting device will come on automatically when th...

Page 67: ...or with different model number a prior analysis and confirmation by CPS is needed Failure to follow this procedure may lead to physical injury or death and void all warranty from CPS WARNING Disconnect all AC and DC Switches before troubleshooting 11 2 Fault Checking If any power output anomaly is observed you may check the following items before contacting CPS Open circuit voltage of the PV array...

Page 68: ...it breaker Then execute discharging wait for 5s and turn on the grid circuit breaker to execute the first system transmission again Table 11 1 Troubleshooting Warn Protect Fault Definition Possible Causes Recommended Solutions Warn 1 Internal communication failure Inverter internal communication in failure 1 Communication circuits inside inverter are loose 2 LCD software problem 1 Observe for 5 mi...

Page 69: ...ice center 4 Warn 0030 Internal warn Internal memory storage error 1 Observe for 5 minutes to see whether the alarm will be eliminated automatically 2 Contact our after sales service center 5 Warn 0040 Internal warn DC or AC SPD is in the off state 1 Observe for 5 minutes to see whether the alarm will be eliminated automatically 2 Contact our after sales service center 6 Warn 0050 Internal warn Te...

Page 70: ...ation is abnormal 1 Observe for 5 minutes to see whether the alarm will be eliminated automatically 2 Contact our after sales service center 9 Warn0080 Internal warn DC overcurrent warning 1 Observe for 5 minutes to see whether the alarm will be eliminated automatically 2 Contact our after sales service center 10 Warn0090 Internal warn DC breaker 1 is abnormal 1 Observe for 5 minutes to see whethe...

Page 71: ...y 2 Contact our after sales service center Protect 1 Over temperature Environmental temperature or temperature inside inverter is too high 1 The external environmental temperature of the inverter is too high 2 The fan is blocked 1 Please confirm that the environmental temperature is within the working range 2 Check whether the air fan is blocked 3 Check whether cooling fan is blocked 4 Observe for...

Page 72: ...ower grid connection line has been disconnected or abnormality has happened 4 Contact our after sales service center 3 Abnormal grid frequency Grid voltage frequency is abnormal or the grid is not detected 1 The grid frequency is abnormal 2 The grid halts 3 The cable between the inverter and the grid is disconnected 4 The inverter has an internal fault 1 Observe for 10 minutes to see whether the a...

Page 73: ...onnected reversely 1 The positive electrode and negative electrode of PV are connected reversely 2 The inverter has internal faults 1 Check whether the positive electrode and negative electrode of PV are connected reversely 2 Contact our after sales service center 6 Excessively low insulation resistance The insulation resistance of the positive to ground or negative to ground of PV exceeds specifi...

Page 74: ...ency stop button 2 After resetting please Contact our after sales service center if the problem still exists 9 Inconsistency of DSP software versions DSP software versions between modules are inconsistent 1 DSP software versions between modules are inconsistent 2 The inverter has internal faults 1 Contact our after sales service center 10 Protect 0010 0200 Internal protection of the inverter Inter...

Page 75: ...ntact our after sales service center Grounding fault Inverter without GFDI function does not have the fault Grounding fault occurs at the DC negative polarity 1 The fuse on the GFDI board has burned up 2 DC negative polarity is not grounded 1 Replace the fuse on GFDI board 2 Check whether the DC negative polarity is grounded or not 3 Contact our after sales service center ...

Page 76: ... WARNING Sand and moisture penetration may affect the performance of electric devices inside the container Do not perform electrical connection in sandy season or when the ambient relative humidity is above 95 Perform electrical connection at fine weather days WARNING Disconnection of the AC DC switches in no way implies that there is no voltage of the cable connection terminals inside the AC and ...

Page 77: ... be more frequent If the container is located in desert areas it is advisable to check thoroughly the container inside and outside and clean completely after the sand storm WARNING Check the module fans inside the container periodically and the fans on top of the cabinet for abnormal operation and abnormal noise If so there may be dust penetrating inside the inverter Stop the inverter and clean th...

Page 78: ...k the temperature and dust of the heat sink Use vacuum cleaner to clean the module if necessary Replace the air filter if necessary Notice Check the air inlet and outlet the device may be damaged by overheating From every six months to annually depending on the dust deposits Warning labels Check if the warning labels are clearly visible Replace them if necessary Once per year Cable connection Chec...

Page 79: ...nd the LCD stop function Simulation shutdown Check the warning labels and other markings for damage or unclearness Replace them if necessary From every six months to annually Software maintenance Optimize software Check each parameter setting From every six months to annually LCD time display Check if the time displayed on the LCD display is correct Replace the button cells on the back of the LCD ...

Page 80: ...n reverse order 12 2 4 Inverter air filter cleaning and replacement The inverter overall adopts the pre and rear air the air cooling design method Open the front and back plate first and then use the 2 cross screwdriver to unscrew the M5 screw on the screen support then replace the filter net as shown in Figure 12 1 Figure 12 1 Replacement of filter net NOTE It is recommended to check and clean th...

Page 81: ...of the container or the component itself If otherwise please contact CPS WARNING If the field work needs to replace the components with products from other manufacturer or with different model number a prior analysis and confirmation by CPS is needed Failure to follow this procedure may lead to physical injury or death and void all warranty from CPS 12 2 6 Spraying Protective Paint Re spray specia...

Page 82: ... 30 C 1500kW 35 C 1500kW 40 C 1500kW 45 C 1500kW 50 C 3000kW 30 C 3000kW 35 C 3000kW 40 C 3000kW 45 C 3000kW 50 C Max AC Output Power 1500kVA 30 C 1500kVA 35 C 1500kVA 40 C 1500kVA 45 C 1500kVA 50 C 3000kVA 30 C 3000kVA 35 C 3000kVA 40 C 3000kVA 45 C 3000kVA 50 C Rated Output Voltage 600Vac Output Voltage Range 15 10 Grid Connection Type 3φ PE Max AC Output Current 1443A 2886A Rated Output Frequen...

Page 83: ... version Guarantee or liability claims for damages of any kind are excluded if they are caused Improper or inappropriate use or install of the product Install or operate the product in unintended environment Install or operate the product without observing relevant safety regulations in the deployment location Ignore the safety warnings or instructions contained in all documents relevant to the pr...

Page 84: ...s about this product please contact us through the following information We will be more than happy to assist you Company SHANGHAI CHINT POWER SYSTEMS CO LTD Website www chintpower com Email service cps chint com Address Building 4 No 3255 Sixian Road Songjiang District Shanghai China Zip 201614 Telephone 86 021 37791222 Fax 86 021 37791222 866003 ...

Reviews: