Models EV1020, EV1220, EV1520
Installation, Operation and Maintenance
Rev.12/16/2020
EV-IOM-A.doc
10
New Floor
12.
Pour 8” to 12” of concrete around the top of the lift / containment assembly and
install rebar to tie in the finished floor as shown in
Fig. 6
.
6 x 6 Support
Lift / Containment
Assembly
1/2-13 x 18
All Thread Rod
1/2-13
Nut and Washer
8"-12"
Rebar
Fig. 6
13.
After the concrete has set up remove the 6 x 6 supports, threaded rods, and
shipping straps. Replace the cover bolts with the ½-13 x 2” HFHB. The shipping
strap bolt replacements are supplied in the hardware box. Torque the bolts to 60
ft-lbs.
14.
Pour concrete floor taking care not to run concrete in or on top of the lift /
containment assembly. The floor should slope away from the lift for drainage.
The floor slope should not accede 1/16" per foot.
15.
DO NOT
use the lift until the concrete has fully cured to 3500 psi.
16.
Install the power unit mounting bracket or floor pedestal using the anchors
provided.
IMPORTANT:
The electric motor must be mounted at least 18 inches
above the finished floor level as per National Electric Code NFPA70. Assemble
the power unit and lock release valve bracket to wall mounting bracket or
pedestal with 5/16-18 cap screws and nuts provided. Refer to
Fig. 5
.
17.
Connect the power unit to an electrical source as shown in
Fig. 7
.