Technical instructions for the commissioning and adjustment 

 

 

7

      

 

 

 

 

 

 

c)  Drill  2  holes  at  the  distance  of  358  mm  on  the  top  side  of  boiler  plating,  and  using  enclosed 

screws 3.9 x 9.5 mm fix boiler control unit CPREG - touch, insert the safety thermostat sensor 
and control unit sensor into the sleeve on the boiler (on the top side on EKO-CK P boiler) and 
connect wires by 4-poles and 6-poles connectors onto the burner and then fix the connectors 
to the burner body. Fix wire cable between the control unit and burner to the boiler casing by 
supplied plastic cable holder (fix cable holder onto boiler casing with tapping screws 3.9 x 16 
mm). 

 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
 

                                    Mounting of the micro switch for lower boiler door 

 

d)  Set the micro switch (1) in lower left corner of the lower front casing of the boiler (3) using 2 

screws, put the cover (2) according to the picture on micro switch and fasten it with the screw. 
Check if lower boiler door, when they are closed, push the micro switch. 

e)  Assembly the pellet tank CPSP-800 according to technical instructions and position it next to 

the right or left boiler side onto horizontal surface. Align tank bottom with the boiler bottom and 
align the front tank side with the front side of boiler plating. 

f)  Place the feeder CPPT-90 into tank and connect it by a transparent flexible tube with a pellet 

burner CPPL-90. Fix one end of transparent flexible tube to the burner (onto the feeding tube) 
to  backfilling  sensor  /  temperature  gauge  on  inlet  tube,  and  other  end  should  be  fixed  to  the 
feeder  so  that  the  tube  will  not  become  loosen.  Transparent  tube  between  the  feeder  and 
burner must be as straight as possible so that pellets can fall smoothly from the feeder into the 
burner (if pellets remain in the tube, it should be straighten and shorten, if necessary). 

g)  Connect  a  wire  for  power  supply  to  the  screw  feeder  CPPT-90  to  the  connector  (2)  on  the 

back side of the control unit CPREG - touch. 

h)  If  sanitary  water  is  prepared  by  using  the  boiler  control  unit,  or  the  system  installed  one  or 

more accumulation tank (CAS) a sanitary water sensor should be fixed to connector 4 instead 
of a jumper wire. 

 

   

h1)  If the sanitary water is prepared with the help of boiler control unit, sensor should 

   

       be placed in domestic hot water tank (Figure 1a). 

 

 

 

h2)    if  it  is  installed  one  or more  accumulation  tanks (CAS)  it  is  necessary  to  set  the 

 

 

       domestic  hot  water  sensor  at  the  lowest  sensor  sleeve  on  the  last  accumulation  

 

 

       tank  (CAS)  or  in  a  sensor  tube  below  the  water  level  we  want  to  warm  up  (see 

 

 

       Figure  1b).  In  this  case  the  hot  water  sensor  has  no  direct  connection  with  the 

 

 

       preparation of hot water (Figure 1b). 

 

i) 

If  used  Telecontrol  or  cascade  manager  they  is  connected  in  place  of  a  room  thermostat 
(Connector 3). 

j) 

A jumper wire is factory installed in the place of room thermostat (connector (3). If an adapter 
is used for ‘’more zones’’ control (optional equipment), a jumper wire in the connector (3) must 
be put. 

k) 

Do  not

  connect  boiler  control  unit  to  power  supply  via  a  built  in  thermostat  on  the  boiler  (if 

there is a thermostat on the upper side of EKO-CK P boiler). 

 

Summary of Contents for Cm Pelet-set 90

Page 1: ...o Glavna 12 40306 Macinec Croatia tel 385 40 372 600 fax 385 40 372 611 TECHNICAL INSTRUCTIONS FOR THE COMMISSIONING AND ADJUSTMENT Cm Pelet set touch 60 90 kW For boilers EKO CK P 70 110 TUPS 90 T 07 2017 E N eng_1 07 ...

Page 2: ... set 90 4 1 Installation of pellet burner and pellet control unit on boiler 4 2 Installation of pellet tank CPSP 800 and pellet feeder CPPT 90 5 Start stop 6 Draught of the chimney 7 Automatic pellet refill 8 Initial setting of the regulation 8 1 Setting the configuration 8 2 Setting the protection valve actuator time 3 3 3 5 5 8 9 10 10 10 11 11 12 ...

Page 3: ...ler control unit CPREG touch 4 pellet feeder CPPT 90 5 pellet tank CPSP 800 3 Technical data Description 1 pellet burner CPPL 90 2 tube for connecting of pellet feeding flexible tube 3 connectors for connecting of burner with control unit 4 Backfilling sensor temperature sensor on inlet tube that is installed tube for connecting of pellet feeding flexible tube backfilling sensor is detailed in the...

Page 4: ...90 Set thermal output kW 60 70 90 Boiler type EKO CK P 70 EKO CK P 90 EKO CK P 110 Pellet tank volume l 800 Pellet tank height mm 1420 Pellet tank depth mm 980 Pellet tank width mm 1010 Supply voltage V Hz 230 50 Boiler width mm 640 690 690 Lower boiler door CPDV mm CPDV 60 70 for burner CPPL 90 for boiler EKO CK P 70 and CPDV 90 110 for boilers EKO CK P 90 i 110 ...

Page 5: ...ker gasket toward door and thinner gasket on the side away from door onto prepared screws on the door then place a feeding box and tighten the screws with enclosed nuts M8 Put a gasket onto the feeding box and put a feeding tube onto it faced toward the pellet tank either on the left or on the right side and tighten it firmly using enclosed screws M4 x 30 Connect 3 pin plug of the backfilling sens...

Page 6: ...Technical instructions for the commissioning and adjustment 6 ...

Page 7: ...r temperature gauge on inlet tube and other end should be fixed to the feeder so that the tube will not become loosen Transparent tube between the feeder and burner must be as straight as possible so that pellets can fall smoothly from the feeder into the burner if pellets remain in the tube it should be straighten and shorten if necessary g Connect a wire for power supply to the screw feeder CPPT...

Page 8: ... 90 and 110 with in built Cm Pelet set 90 on heating installation with accumulation tank 1 Boiler EKO CK P 70 90 110 with in built Cm Pelet set 90 2 Accumulation tank CAS 3 Heating pump between boiler and accumulation tank CAS 4 Sanitary water sensor at the lowest sensor sleeve on the accumulation tank 5 3 way thermostat valve for outlet protection as ESBE VTC 512 VTC 531 LTC 141 or Laddomat 21 or...

Page 9: ...m it pressing the OK button To stop the boiler press ON OFF button and confirm it pressing the OK button 6 Draught of the chimney Chimney of appropriate size is one of conditions for proper operation of the boiler Chimney has to be select according to diagram for solid fuel firing see Technical instructions EKO CK P or EKO CKB P or a chimney with the following minimum draughts has to be select for...

Page 10: ...wer supply for the filling system LED main switch on when there is power supply Operation mode switch select working mode 0 OFF disabled 1 Auto filling working until tank sensor stops it 2 Manual filling working until manual switching off doesn t working according to tank sensor LED filing on when filling is working manual or auto ...

Page 11: ...press Installation button SERVICE PIN required 3 In Installation menu press Commissioning button 4 In Commissioning menu press Configuration button 5 In Configuration menu press Configuration button 6 In Configuration menu set scheme 1 scheme CODE 3 characters 2 buttons for changing the values 3 scheme description 7 Set scheme current B 0 0 Confirm it with OK button blue button ...

Page 12: ...tton 3 In Valve time setting set protection valve actuator opening closing time it depends on the build in protection valve actuator Centrometal d o o shall not be responsible for possible incorrect data caused by printing errors or errors during transcription and in any case it reserves the right to modify its products deemed to be required and useful without any prior notification 1 07 Macinec 0...

Reviews: