Installing the i-Vu® Open Router
i-Vu® Open Router
CARRIER CORPORATION ©2020
Installation and Start-up Guide
All rights reserved
5
Wiring the i-Vu® Open Router for power
WARNING
Do not apply line voltage (mains voltage) to the controller's ports and terminals.
CAUTIONS
•
The i-Vu® Open Router is powered by a Class 2 power source. Take appropriate isolation measures when
mounting it in a control panel where non-Class 2 circuits are present.
•
Carrier controllers can share a power supply as long as you:
•
Maintain the same polarity.
•
Use the power supply only for Carrier controllers.
To wire for power
1
Make sure the i-
Vu® Open Router’s power switch is in the
OFF
position to prevent it from powering up before
you can verify the correct voltage.
2
Remove power from the power supply.
3
Pull the screw terminal connector from the router's power terminals labeled
24 Vac/Vdc
and
Ground
.
4
Connect the transformer wires to the screw terminal connector.
5
Apply power to the power supply.
6
Measure the voltage at the i-Vu® Open
Router’s power input terminals to verify that the voltage is within the
operating range of 21.6
–
26.4 Vac or 23.4 - 28.6 Vdc.
7
Insert the screw terminal connector into the i-Vu® Open Router's power terminals.
8
Turn
on
the i-Vu® Open Router's power.
9
Verify that the Run LED (a dot in the lower right corner of the
Module Status
LED) begins blinking. The
Module
Status
LED will display
8
for about 5 seconds and then reverts to
0,
until controllers have been found and
downloaded. There is a chase pattern when the router is running with no errors.