CAMPO EQUIPMENT CO. LTD. (ECOBLAZE)
6 Carson Court, Brampton, ON, CANADA, L6T 4P8
Tel: (905) 793-2525 | Fax: (905) 793-8768 |
www.campoequipment.com
P a g e
|
16
TEMPERATURE CONTROLLER AND THERMOCOUPLE
The temperature controller protocols should be checked every heating season to ensure the burner will shutdown if
temperature exceeds 290F at the outlet duct. This can be accomplished by restricting the air flow through the unit.
After tests are complete, remove restrictors as both inlet and outlet ducts must be open for proper operation.
The fan switch setting of 110F and time delay of 1 minute has been selected to allow for preheating of the heat
exchanger to ensure that only heated air is allowed to enter the space. Upon satisfying the need for heat, the fan
switch will continue to run the supply fan until the heat exchanger has cooled sufficiently. This feature will help prolong
the life of the heat exchanger. The fan switch must be replaced if the fan motor does not shut off after the heat
exchanger has cooled down.
Fan Switch Protocols
Fan Turns on at 110F OR time delay of 1 minute
There is a redundant 150F high limit switch.
During cool down the unit cools to 80F and then shuts down.
ELECTRICAL
Ensure all conduit (BX) connectors are tight. Open control panel door and burner compartment and check connections
are tight and no frayed wires exposed.
FAN
Check for dust or dirt build up on blades. Run heater to check for fan vibration. Replace fan blade if vibration is
noticeable. The flow of combustion and ventilation air must not be obstructed. Be sure to check the fan assembly and
ensure that the motor and blade are operating properly.
MOTOR
No lubrication is necessary since the bearings are the sealed type. Clean motor of existing dust or dirt.
GAS TRAIN (annual basis)
Connect gas supply to gas train with gas safety shut-off valves closed. Spray all of gas train components including
safety shut-off valves with soap and water solution to check for leaks. Open safety shut off valves on gas train and
spray with soap and water solution to check for leaks.
HEAT EXCHANGER
If a smoky condition continues even after adjusting the air assembly, the heat exchanger should be thoroughly
cleaned.
FUEL FILTER (OIL OPERATION)
Replace cartridge every six months of normal usage.
NOTE: FLOW OF COMBUSTION AND VENTILATION AIR CANNOT BE OBSTRUCTED
FLAME DETECTOR (OIL OPERATION)
When doing maintenance, turn on machine and run. After having machine run for a few minutes, press red button on
primary control. Hold for one second and then release. If light flashes once or twice or three times, cad cell is
functioning properly. If flashes four times, check alignment and proper flame. If correct a cleaning of the face of the
cad cell with a soft non-abrasive cloth is recommended. If light flashes 4 times, follow above steps. If flashing four
times persists, replace cad cell.