ITH-Series Technical Manual
Page 15
Cambridge
Engineering
Inc.
Installation
H
EATER AND
B
AFFLE
I
NSTALLATION
Locate the burner gasket provided, bolt the burner in place on the tube flange with provided
hardware.
Burner must never be installed in a tilted position.
The sense electrode of the burner
cup should be in the 12 o’clock position (Figure 10).
Figure 10: Burner Gasket Installation
If required for your heater model (refer to Table 1), install the baffle at the end of the heat
exchanger. The small tab on the baffle is folded over the end of the tube and clamped in place by
the vent connector and vent system, (Figure 11).
Note:
Baffles are always placed at the end of the last heat exchanger tube length, with the
exception of the special configuration ITH-205 with a 50
′
tube length, (
Figure 3
) for more
details.
Note:
Baffles are either one or two sections (each section is 6' in length). Multiple sections are
simply clipped together. Where stainless and aluminized sections are supplied, always
place the stainless steel section closest to the burner. The easiest installation method is to
pull the baffle through the tube using a long wire.
Figure 11: Baffle Installation
Note:
Burner MUST NEVER
be tilted sideways.
Burner
Assembly
Gasket
Tube
Flange
Blower shown
with optional
Air Inlet Collar Kit
Bend Tab
over End
of Tube
at 6 O'clock
position
Vent
Adapter
Install Baffle
as required in
last section
of tube