Chapter 5: Installation
234
7
Ground the antenna cables to the supporting structure within 0.3 meters (1 foot) of
the ODU and antennas using the Cambium grounding kit (part number 01010419001):
8
Fix the antenna cables to the supporting structure using site approved methods.
Ensure that no undue strain is placed on the ODU or antenna connectors. Ensure that
the cables do not flap in the wind, as flapping cables are prone to damage and induce
unwanted vibrations in the supporting structure.
Note
A video on weatherproofing procedure can be found at:
https://www.youtube.com/watch?v=a-twPfCVq4A
Assembling t he PMP 4 50 i AP 5 GHz sect or ant enna and at t aching t o t he
radio
To assemble a PMP 450i Series AP antenna, perform the following steps.
Summary of Contents for PMP 450 AP
Page 92: ...Chapter 2 System hardware 92 Figure 29 MicroPoP Omni antenna implementation pattern Vertical ...
Page 134: ...Chapter 3 System planning 134 Figure 51 Mast or tower installation ...
Page 135: ...Chapter 3 System planning 135 Figure 52 Wall installation ...
Page 136: ...Chapter 3 System planning 136 Figure 53 Roof installation ...
Page 137: ...Chapter 3 System planning 137 Figure 54 GPS receiver wall installation ...