7 Commissioning
Shenzhen BYD Electronic Co., LTD
36
HVS&HVM Operating Manual
7.3.
Switch on and Commission the Inverter
Procedure:
1.
Mount and connect the inverter according to the inverter manufacturer`s instruction.
2.
Commission and configure the inverter according to the inverter manufacturer`s
instruction.
If the battery information could be read correctly, it means the connection between the battery
system and the inverter is all right.
If the LED still flashes blue, and/or there are some battery errors shown at the inverter, go to
the Chapter 11 Troubleshooting of this manual and also read the Service Guideline and
Checklist.