7.
Commissioning
7.1.
Switch on the Battery System
Requirements:
•
The power cable connection between the battery system and the inverter is switched off.
•
The inverter must be correctly mounted.
•
All cables must be correctly connected.
•
The Operating Panel is well fixed.
Procedure:
INVERTER
1
(if available)
2
2
2
1. Switch on the air switch between the battery and inverter if there is any.
2. Open
the plastic cover on the right side of the BCU.
3. Push up
the air switch from the Off position to On.
4. The LED starts to flash (0.5s white, 0.5s blue)
for
a while, and then turns into white, which
means the battery system is ready to work.
5. If it is failed to switch on the
battery
system,
read Chapter 11 Troubleshooting and also the
Service Guideline and Checklist.
IF THE
PROBLEM STILL CANNOT
BE SOLVED, CONTACT
OUR LOCAL AFTER-SALE
SERVICE WITHIN 48 HOURS.