VII. Venting
H. Assembly of Centrotherm InnoFlue Vent Systems
H. Assembly of Centrotherm InnoFlue Vent Systems
1.
This boiler has been approved for use with the Centrotherm InnoFlue single wall Polypropylene vent system to be provided
by the installer.
WARNING
Asphyxiation Hazard. Follow these instructions and the installation instructions included by the
original Polypropylene venting component manufacturers, Centrotherm. Failure to do so could cause
products of combustion to enter the building, resulting in severe property damage, personal injury
or death. Where a conflict arises between Centrotherm instructions and these instructions, the more
restrictive instructions shall govern.
Do not mix vent components or joining methods for listed manufacturers.
Examine all components for possible shipping damage prior to installation.
All condensate that forms in the vent must be able to drain back to the boiler.
2. Assemble the vent system, starting at the boiler:
a. The vent adaptor has three different inside diameters. The middle inside diameter accepts 3” nominal InnoFlue (Figure
7.27). A locking band clamp in the adaptor prevents the vent pipe from coming out of the adaptor once it is installed
and tightened. Lubricate the upper gasket in the vent adaptor with water and insert the first piece of 3” InnoFlue into the
adaptor until it bottoms out. Tighten locking band clamp to secure vent pipe.
b. Assemble the next piece of 3” InnoFlue.
c. For each joint, verify that the gasket is evenly seated in the bell (female) end of the pipe. Lubricate this gasket with
Centrocerin # IACE50. Slide a connector ring over the male end of the pipe to be joined as shown in Figure 7.44. Push
the male end of the next section of pipe into the bell until it bottoms out, then back out 1/4” to provide room for thermal
expansion. Push hook on connecting ring over the bell end of the first section of pipe as shown in Figure 7.44.
d. Assemble the rest of the vent system per the manufacturer’s installation instructions, being sure to pitch horizontal
sections back towards the boiler 5/8”/ft.
e. Support each horizontal pipe section with a minimum of one wall strap each and at intervals not exceeding 39in.
Figure 7.44: InnoFlue Connector Ring Installation
Summary of Contents for K2WTC
Page 81: ...81 107774 01 9 17 X Domestic Hot Water Piping continued Figure 10 1 Domestic Hot Water Piping ...
Page 88: ...88 107774 01 9 17 XI Wiring continued XI Wiring continued ...
Page 89: ...89 107774 01 9 17 Figure 11 7 Internal Wiring Connections Diagram XI Wiring continued ...
Page 100: ...100 107774 01 9 17 Lighting and Operating Instructions XII Start Up and Checkout continued ...
Page 141: ...141 107774 01 9 17 XVI Repair Parts continued ...
Page 144: ...144 107774 01 9 17 XVI Repair Parts continued ...
Page 147: ...147 107774 01 9 17 XVI Repair Parts continued ...
Page 149: ...149 107774 01 9 17 XVI Repair Parts continued ...
Page 151: ...151 107774 01 9 17 XVI Repair Parts continued 120 121 122 123 124 125 126 127 ...
Page 158: ...158 107774 01 9 17 SERVICE RECORD DATE SERVICE PERFORMED ...
Page 159: ...159 107774 01 9 17 SERVICE RECORD DATE SERVICE PERFORMED ...