5.    MAINTENANCE OF LOW WATER CUTOFF 

DEVICES

   

Probe and float type low water cutoff devices require annual 

inspection and maintenance.

Les interrupteurs à bas niveau d’eau de type sonde ou 

de  type  flotteur  doivent  être  inspectés  et  entretenus 

annuellement.

A. Probe Type Low Water Cut Off 

 Although these 

devices are solid state in design, the probe is  

 

exposed to possible contamination in the boiler    

water. 
It is important to physically remove the probe  

from the boiler tapping annually and inspect it for 

accumulation of scale or sediment.

  Following these steps inspect, clean and/or 

replace the probe:

1.  Turn off electric service to the boiler.
2.  Drain boiler water to a level below the tapping 

for the probe.

3.  Disconnect the wiring connections between 

the low water cutoff and the probe.

4.  Dismount the low water cutoff control from the   

probe.

5.  Unscrew the probe from the boiler tapping. 
6.  Inspect that portion of the probe that is 

exposed to the boiler water for scale or 

sediment buildup.

7.  Light deposits may be removed by wiping the  

probe with a damp cloth. Wiping the probe 

with a cloth soaked in vinegar will remove 

more tenacious lime deposits. The most 

stubborn deposits may be removed from the 

probe by using diluted amount (3 part of water 

to 1 part) of phosphoric acid (H2PO4). 

   Clean firetubes with flue brush and reinstall

 

turbulators. If turbulators are corroded or    

deteriorated, replacing them will ensure a high 

level of boiler efficiency. Remove soot and rust 

and reseal the boiler.

 

Turbulator quantities are shown below. Access to 

turbulator replacement is from the front smokebox. 

Turbulators should be installed and removed from 

the front of the boiler only.

   Series 4FH: All 4FH Series boilers come equipped 

with turbulators in all third pass tubes (upper rows 

of tubes), with quantities as follows:

  1. Sizes 63A/107A quantity of (18).
  2. Sizes 127A/209A quantity of (22).
  3. Sizes 240A/345A quantity of (40).
  4. Sizes 360A/450A quantity of (46).
  5. Sizes 563A/675A quantity of (56).
  6. Sizes 827/993 quantity of (54).
  7. Sizes 1157/1323 quantity of (72).

  8. Size 1654 quantity of (93).

  9. Size 1985/2315 quantity of (109).

  10. Size 2645 quantity of 113.
  11. Size 3075A quantity of (151).

4.   BOTTOM BLOWDOWN PROCEDURE 

  

Burnham high pressure steam boilers are equipped 

with two bottom blowdown connections. Bottom 

blowdown should be done while the boilers are under 

pressure, with the burner off or at low fire. There should 

be two quick-opening valves and one downstream 

slow-opening valve. Open the slow-opening valve first. 

Slowly open the front quick-opening valve to warm up 

the piping and blowdown separator. Open the valve for 

a few seconds with a quick blast to flush out sludge and 

sediment from the bottom of the boiler. Do not lower the 

boiler water level by more than ½

"

. Close the valve, then 

repeat for the rear quick-opening valve. Close the slow-

opening valve. Make sure all valves are closed. A water 

treatment consultant can recommend an appropriate 

manual blowdown schedule, but is generally done once 

per shift.
Water columns should be blown down once per shift to 

keep the internal parts of the pump control and low water 

cutoff free from sediment. If the boiler is equipped with a 

“water column bypass” switch, depress the switch while 

performing the blowdown. Close the valve and release 

the switch.

Summary of Contents for 4FHL-107A

Page 1: ...hnician BEFORE installing read all instructions in this manual and all other information shipped with the boiler Post all instructions and manuals near the boiler for reference by service personnel Pe...

Page 2: ...es having jurisdiction should be consulted before installations are made C All wiring on boilers installed in Canada shall be made in accordance with the Canadian Electrical Code and or Local Regulati...

Page 3: ...ne Burner boiler systems produce steam or hot water in a pressurized vessel by mixing extremely flammable gaseous liquid or solid fuels with air to produce combustion and very hot products of combusti...

Page 4: ...e s ret sont absents ou install s l aide de cavaliers Ne pas faire fonctionner si une commande un interrupteur un composant ou un dispositif est entr en contact avec de l eau Improper installation adj...

Page 5: ...e combustible contiennent de l alumine de la silice des m taux lourds du monoxyde de carbone des oxydes d azote des ald hydes ou d autres substances toxiques ou dangereuses pouvant causer la mort ou d...

Page 6: ...ted piping electrical and control systems used and maintained in the boiler room Le terme syst me de br leur chaudi re utilis dans ce manuel signifie tout quipement m canique ou lectrique y compris la...

Page 7: ...esting Controls 16 17 Initial Cleaning Steam Boilers 17 Initial Cleaning Water Boilers 17 18 Water Boiler Operation 18 Boiler Water Treatment 18 pH or Alkalinity Test 18 Warnings about Frequent Water...

Page 8: ...ombustion efficiency of over 80 This manual gives the necessary information for the proper installation operation maintenance and service of units For special installation problems contact Burnham Com...

Page 9: ...um capacity and will light off and have stable and consistent combustion On installations where a natural draft stack is used causing high breeching drafts the boiler locking blade damper on boilers e...

Page 10: ...altitude installations above 1 000 ft An adjustment of 3 5 per 1 000 ft of elevation is recommended 6 LOCATION OF ASME STAMPING DATA The ASME stamping data is located as follows 1 Series 4FH Sizes 63...

Page 11: ...the boiler warms up If formation of condensate persists the low limit should be adjusted upward until condensate no longer forms Water boilers and low pressure steam boilers must have a set LFH at 12...

Page 12: ...es in the boiler metal These stresses can cause damage to the boiler by loosening tubes or in more severe instances can crack tube sheet ligaments furnaces or waterlegs B If temperature differentials...

Page 13: ...MANUAL 9 RELIEF VALVES Boiler relief valves are normally shipped loose and have been properly sized for your boiler The aggregate capacity of the relief valves as stamped on the valve rating plates mu...

Page 14: ...14 FIGURE 4 TS 71 130 D INSTALLATION INSTRUCTIONS FIGURE 3 TS 71 176 B...

Page 15: ...15 TS 71 131 D FIGURE 5 TS 3 101 4 INSTALLATION INSTRUCTIONS FIGURE 6...

Page 16: ...control Avant que l installation de la chaudi re soit consid r e comme termin e v rifier le fonctionnement de ses dispositifs de contr le en particulier les interrupteurs bas niveau d eau et le contr...

Page 17: ...afety relief valve using extreme care to avoid damaging it A Check Operating Control Raise and lower operating control setting as required to start and stop burner B Warning Check High Limit Control J...

Page 18: ...WATER TREATMENT Boiler water treatment will help maximize the effectiveness and prolong the life of pressure vessels The general objectives of boiler water treatment are A Remove corrosive gases from...

Page 19: ...chaudi re par l oxyg ne provoque la corrosion des composants en fer et en acier et peut mener une d faillance La garantie standard de Burnham ne couvre pas les probl mes caus s par la contamination de...

Page 20: ...emperature to increase even if the gauge pressure is 0 It is better to allow the entire system to cool gradually never force cool the boiler as damage can also be inflicted due to thermal shock G When...

Page 21: ...rbulator replacement is from the front smokebox Turbulators should be installed and removed from the front of the boiler only Series 4FH All 4FH Series boilers come equipped with turbulators in all th...

Page 22: ...to solder joints on bellows and float when this type of control is used Check the float for evidence of collapse and check mercury bulb where applicable for mercury separation or discoloration DO NOT...

Page 23: ...at the end of heating season Drain off boiler water until it runs clear while holding the boiler temperature between 180 and 200 F Then refill to top of gauge glass B Water Boilers Since a water boile...

Page 24: ...ion Safety Controls Flame Failure Weekly Operator If flame display installed read and log for both pilot and main flames notify service organization if readings are very high very low or fluctuating r...

Page 25: ...ition Interlock Annually Service Technician Refer to burner instructions Low Fire Start Interlock Annually Service Technician Refer to burner instructions Automatic Changeover At Least Annually Servic...

Page 26: ...26...

Page 27: ...27...

Page 28: ...Product under conditions varying materially from those under such Products is usually tested under industry standards as of the shipment time C Any damage to the Product due to abrasion erosion corro...

Reviews: