Commissioning the heating system
8
Logano GB125 oil condensing boiler - Technical specifications are subject to change without prior notice.
41
8.5
Starting the burner
For further commissioning steps, follow the sequence of
burner commissioning. For this, it is essential that you
observe the
burner documentation.
8.6
Installing the burner cover
B
Hook the burner cover into the hooks of the boiler
casing.
B
Secure the burner cover with both lateral screws.
8.7
Setting the programming
unit/control unit
B
Check and make sure that the following settings on
the programming unit are set:
•
Automatic operating mode
•
Required room temperature
•
Required DHW temperature
•
Required heating program
After completion of the commissioning steps
B
Set both rotary selectors on the control unit to "AUT"
(automatic mode). The programming unit takes con-
trol of the panel in this setting.
Fig. 38
Fitting the burner cover
RISK TO LIFE
from electricity.
B
Only operate the boiler with its cover fit-
ted.
Fig. 39
Programming unit (e.g. RC35, with flap open)
7 747 011 453-17.1RS
USER INFORMATION
B
For information regarding the operati-
on, e.g. selection of temperatures, see
the
unit.
Fig. 40
Setting the control unit