Commissioning the heating system
9
Logano G215 WS - We reserve the right to make any changes due to technical modifications.
46
9.7
Commissioning report
z
Sign all commissioning work as completed and enter
the relevant date.
Commissioning steps
Page
Actual values
Comments
1
.
Fill heating system and check all connections for leaks
37
__________ bar
2
.
Create operating pressure
– Adjust the green field on the pressure gauge
– Bleed the heating system
– Adjust the expansion vessel inlet pressure (
Î
see the expansion
vessel documentation)
42
__________ bar
3
.
Check the combustion air supply and the flue gas routing
4
.
Start up the control device (
Î
see the control device documentation)
43
5
.
Start up the burner (
Î
see the burner documentation)
43
6
.
Check the flue gas temperature, and raise if
required
43
__________ °C
7
.
Check the high limit safety cut-out (STB)
44
8
.
Match the control device settings to the customer's requirements
(
Î
control device documentation)
9
.
Provide the system user with information and hand over all relevant
technical documentation
Confirm that commissioning was carried out by a properly qualified
person
Company stamp/signature/date
USER NOTE
z
Inform your customer of the correct fuel
type and enter it into the table (
Î
boiler
operating instructions).