Ozone Swim 1000, 2000 and 3000 series User Manual
–
JULY 2017 ENG rev 2.0
P a g e
5 | 15
Installation Guide
Note:
If this system is installed below water level, ensure you have a drain
valve fitted to the ozone outlet
Step 1:
Mount Ozone Swim control unit a maximum of 1.5 meters from the filter and chlorine cell.
Fit two screws 380mm apart (screws supplied for control box). Install the Ozone Swim
control unit a minimum of 900mm above ground level in an area protected from the
elements to eliminate possible damage from severe weather conditions. (if system is below
water level, install drain valve as per instructions)
Step 2:
Plumb chlorine cell onto return pipe after filter, ensuring there is a gas trap (see images
below)
Step 3:
Plumb Ozone injector manifold after chlorine cell on the return line of the pool ensuring
direction of ozone injector manifold is correct.
Step 4:
Connect supplied Teflon tubing (see label on Teflon tubing for direction ensuring non-return
valve is in the correct direction) onto the ozone injector manifold by connecting to the
compression fitting on venturi.
Step 5:
Connect the chlorine cell cable to the three colour coded terminals located on chlorine cell.
(Terminals need to be slightly crimped for snug fit).
Step 6:
Ensure appropriate salt/mineral levels are achieved (3500ppm) and dissolved. (confirm with
builder that chemicals can be added to the pool)
Step 7:
Leave plumbing to cure for a 24-hour period for best results.