Installation

 

Bradmar

 Restroom Partitions, Floor-Mounted with Overhead Brace — Series 400

Bradley 

• 

HDWP-INSTR-013 Rev. K; ECN 12-14-012

 

10/1/2014

11a Urinal Screens with Stirrup Brackets (Optional)

Before installing the urinal screen components, 

determine the correct location for your application.

Draw a plumb line on all walls 

representing urinal screen 

centers (see chart below for 

measurements). These marks 

represent hole centerlines for 

the brackets. Use a level to 

transfer that mark to all other 

plumb lines

 .

A

Place the center of each stirrup bracket at each 

established level line. Center the bracket opening 

on the plumb line. Using the bracket as a template, 

mark the hole locations on the wall . Remove the 

bracket and drill a Ø 

⁵⁄₁₆

" x min. 2" (51mm) deep 

hole at each hole location .

B

Place the bottom of each urinal screen 18" (457mm) 

up from floor. Establish a 1" (25mm) gap between 

the finished wall and urinal screen edge. A spacer 

may help to support the weight of the screen and 

establish the appropriate distances.

D

Insert the plastic anchors in all 

holes and secure the brackets with 

the #14 x 2" screws provided .

C

Drill Ø ¼" holes through the screen at 

each bracket hole

 . Secure the screen 

to the brackets with #10-24 x ¾" barrel 

nuts and #10-24 x ¾" shoulder screws 

provided .

E

Dim . "A"

Dim . "B"

Dim. "C"

estab

lished

 

level line

ur

inal

 plumb

 line

floor

Dim . "A"

Dim . "B"

Dim. "C"

15" (381mm) for 42" (1067mm) screens or

18" (457mm) for 48" (1219mm) screens

15" (381mm) for 42" (1067mm) screens or

18" (457mm) for 48" (1219mm) screens

24" (610mm) for 42" (1067mm) screens or 

24" (610mm) for 48" (1219mm) screens

Summary of Contents for Bradmar 400 Series

Page 1: ...enance department Compliance and conformity to local codes and ordinances is the responsibility of the installer Separate parts from packaging and make sure all parts are accounted for before discardi...

Page 2: ...ar saw Two spring clamps and drill bits Power drill or screw gun with drill bit extension Tape measure and 4 level ceramic tile and masonry drill bit Hammer drill Spacer 14 356mm high and strong enoug...

Page 3: ...present the hole center line of the stirrup brackets Use a level to transfer that mark to all other plumb lines C Panel plumb line 63 1600mm 41 1054mm A B B1 A1 C C C C C C C C C 20 508mm C L C L C L...

Page 4: ...Remove the bracket and drill a hole min 2 51mm deep at each hole location B One Eared Bracket Two Eared Bracket 2 Continuous Brackets to Wall Standard established level line pilaster panel plumb line...

Page 5: ...Measure down from the top of the pilaster and place a mark on the pilaster split centerline at dimensions at 13 343mm and 67 1715mm Pilaster shown is for reference only Actual pilaster varies dependi...

Page 6: ...Split A B C U Bracket H Bracket Dim A 19 483mm 13 343mm Dim B 40 1029mm 67 1715mm Dim C 62 1575mm Secure the stirrup brackets to the pilasters using the 14 x screws provided Refer to step 4 for locat...

Page 7: ...13mm between the panel and pilaster Using the bracket as a template drill holes through the pilaster at each pilaster bracket hole Secure the pilaster to the bracket with 10 24 x barrel nuts and 10 24...

Page 8: ...m between the panel and pilaster Using the brackets as a template drill holes through the pilaster at each pilaster bracket hole Secure the pilaster to the bracket with 10 24 x barrel nuts and 10 24 x...

Page 9: ...spacing between the pilasters for the doors is the correct dimension On the back of each pilaster starting with the first pilaster drill a hole through one face of the headrail only Using this hole as...

Page 10: ...rt the spring and the top pin into the pilaster top Move the top of the door into position while pushing the top pin into the pilaster Release the top pin and force the pin to bottom out in the door C...

Page 11: ...3 Top Pin Lip Lip 3 76mm 3 Top Pintle 3 Bottom Pintle Assembly Notch Feature for adjacent door strike 19mm 1 44mm 13mm Drill first hole as shown Attach and align heat sink with single screw 6 x flat h...

Page 12: ...a 8 x 1 flat head Phillips drive screw To adjust spring tension use a torx screwdriver and turn the torx head clockwise approximately one complete revolution Insert a 1 38mm long nail into the hole th...

Page 13: ...d to the shoe and that the headrail is installed Determine the door swing by facing the compartment from the outside Refer to your submittal drawings to determine each specific door swing for your app...

Page 14: ...or Use tape to hold the hinge sets together H Place the upper blank of the top hinge set on the door 2 51mm from the top Using the hinge as a template drill a x 1 25mm deep pilot hole into the edge of...

Page 15: ...the door so that the slide bar is centered in the slot on the strike keeper The leading edge of the latch should be positioned approximately 10mm from the door edge Install the coat hook in the upper...

Page 16: ...so that the slide bar is centered on the strike keeper The leading edge of the latch should be positioned approximately 1 25mm from the door edge Install the coat hook according to local codes For su...

Page 17: ...as a template drill a pilot hole into the door 19mm deep Secure the latch to the door using hardware provided B With the door in the closed position mount the latch on the inside of the door so that...

Page 18: ...A B G F H With the door in the closed position mount the latch on the inside of the door so that the center of the slide bar is 27 699mm from the top of the door The leading edge of the latch should b...

Page 19: ...16 and larger B Using the bracket as a guide drill a x deep pilot hole at each screw hole location The stiffener bracket is installed on the largest side of a pilaster split B Using the bracket as a g...

Page 20: ...hole locations on the wall Remove the bracket and drill a x min 2 51mm deep hole at each hole location C Place the bottom of the continuous bracket at the established level line Center the bracket ope...

Page 21: ...e hole locations on the wall Remove the bracket and drill a x min 2 51mm deep hole at each hole location B Place the bottom of each urinal screen 18 457mm up from floor Establish a 1 25mm gap between...

Reviews: