background image

8

Bradmar

 Restroom Partitions, Floor-Mounted with Overhead Brace — Series 400

 

Installation

10/1/2014 

Bradley

 • 

HDWP-INSTR-013 Rev. K; ECN 12-14-012

6a Panels and Pilasters with Stirrup Brackets (Optional)

Pilasters located at walls should be mounted first. Start at one end and install a panel, then a pilaster. 

Continue alternating until installation is complete. When installing in an alcove or in-corner alcove, use an "H" 

bracket to secure the pilaster to the panel.

When installing pilasters at walls, the gaps range 

from 

½

" to 1

¼

" (13mm to 32mm). Refer to your 

submittal drawing for your gap sizes.

Check to make sure the pilasters are plumb and level to each other. The pilaster height can be adjusted with 

the leveling screw that was placed at the bottom of the pilaster (see page 5 for attaching leveling bolt).

Refer to your submittal drawing and leave the appropriate 

gaps. Standard gap is 1" (25mm) between the panel and 

wall and 

½

" (13mm) between the panel and pilaster.

Using the brackets as a template, drill Ø ¼" 

holes through the pilaster at each pilaster 

bracket hole. Secure the pilaster to the bracket 

with #10-24 x ¾" barrel nuts and #10-24 x ¾" 

shoulder screws provided .

Using the hole in the shoe as a template, drill a 

Ø ¼" hole through the pilaster and secure the 

shoe to the pilaster with #10-24 x ¾" barrel nuts 

and #10-24 x ¾" shoulder screws provided . 

Using the hole in the shoe as a template, drill a Ø ¼" 

hole through the pilaster and secure the shoe to the 

pilaster with #10-24 x ¾" barrel nuts and #10-24 x ¾" 

shoulder screws provided . 

Set the pilaster into the shoe while at the 

same time placing into the wall brackets.

A

Place a panel on the spacer and insert the panel into 

the wall brackets.

Set the pilaster into the shoe while at the same time 

placing the brackets around the panel.

A

B

Using the brackets as a template, drill Ø ¼" holes through 

the panel at each panel bracket hole. Secure the panel to 

the brackets with #10-24 x ¾" barrel nuts and #10-24 x ¾" 

shoulder screws provided .

B

C

C

Spacer 14" (356mm)

Aluminum heatsink 

on bottom of panel.

Pilasters at Wall

Pilasters with Panels

Summary of Contents for Bradmar 400 Series

Page 1: ...enance department Compliance and conformity to local codes and ordinances is the responsibility of the installer Separate parts from packaging and make sure all parts are accounted for before discardi...

Page 2: ...ar saw Two spring clamps and drill bits Power drill or screw gun with drill bit extension Tape measure and 4 level ceramic tile and masonry drill bit Hammer drill Spacer 14 356mm high and strong enoug...

Page 3: ...present the hole center line of the stirrup brackets Use a level to transfer that mark to all other plumb lines C Panel plumb line 63 1600mm 41 1054mm A B B1 A1 C C C C C C C C C 20 508mm C L C L C L...

Page 4: ...Remove the bracket and drill a hole min 2 51mm deep at each hole location B One Eared Bracket Two Eared Bracket 2 Continuous Brackets to Wall Standard established level line pilaster panel plumb line...

Page 5: ...Measure down from the top of the pilaster and place a mark on the pilaster split centerline at dimensions at 13 343mm and 67 1715mm Pilaster shown is for reference only Actual pilaster varies dependi...

Page 6: ...Split A B C U Bracket H Bracket Dim A 19 483mm 13 343mm Dim B 40 1029mm 67 1715mm Dim C 62 1575mm Secure the stirrup brackets to the pilasters using the 14 x screws provided Refer to step 4 for locat...

Page 7: ...13mm between the panel and pilaster Using the bracket as a template drill holes through the pilaster at each pilaster bracket hole Secure the pilaster to the bracket with 10 24 x barrel nuts and 10 24...

Page 8: ...m between the panel and pilaster Using the brackets as a template drill holes through the pilaster at each pilaster bracket hole Secure the pilaster to the bracket with 10 24 x barrel nuts and 10 24 x...

Page 9: ...spacing between the pilasters for the doors is the correct dimension On the back of each pilaster starting with the first pilaster drill a hole through one face of the headrail only Using this hole as...

Page 10: ...rt the spring and the top pin into the pilaster top Move the top of the door into position while pushing the top pin into the pilaster Release the top pin and force the pin to bottom out in the door C...

Page 11: ...3 Top Pin Lip Lip 3 76mm 3 Top Pintle 3 Bottom Pintle Assembly Notch Feature for adjacent door strike 19mm 1 44mm 13mm Drill first hole as shown Attach and align heat sink with single screw 6 x flat h...

Page 12: ...a 8 x 1 flat head Phillips drive screw To adjust spring tension use a torx screwdriver and turn the torx head clockwise approximately one complete revolution Insert a 1 38mm long nail into the hole th...

Page 13: ...d to the shoe and that the headrail is installed Determine the door swing by facing the compartment from the outside Refer to your submittal drawings to determine each specific door swing for your app...

Page 14: ...or Use tape to hold the hinge sets together H Place the upper blank of the top hinge set on the door 2 51mm from the top Using the hinge as a template drill a x 1 25mm deep pilot hole into the edge of...

Page 15: ...the door so that the slide bar is centered in the slot on the strike keeper The leading edge of the latch should be positioned approximately 10mm from the door edge Install the coat hook in the upper...

Page 16: ...so that the slide bar is centered on the strike keeper The leading edge of the latch should be positioned approximately 1 25mm from the door edge Install the coat hook according to local codes For su...

Page 17: ...as a template drill a pilot hole into the door 19mm deep Secure the latch to the door using hardware provided B With the door in the closed position mount the latch on the inside of the door so that...

Page 18: ...A B G F H With the door in the closed position mount the latch on the inside of the door so that the center of the slide bar is 27 699mm from the top of the door The leading edge of the latch should b...

Page 19: ...16 and larger B Using the bracket as a guide drill a x deep pilot hole at each screw hole location The stiffener bracket is installed on the largest side of a pilaster split B Using the bracket as a g...

Page 20: ...hole locations on the wall Remove the bracket and drill a x min 2 51mm deep hole at each hole location C Place the bottom of the continuous bracket at the established level line Center the bracket ope...

Page 21: ...e hole locations on the wall Remove the bracket and drill a x min 2 51mm deep hole at each hole location B Place the bottom of each urinal screen 18 457mm up from floor Establish a 1 25mm gap between...

Reviews: