Commissioning
Sense II – 6 720 818 367 (2015/10)
5
Commissioning
5.1
Overview over the commissioning steps
1. Mechanical structure of the system (observe instructions
for all assemblies and components)
2. System fill, treatment and pressure test
3. Electrical wiring
4. Setting coding addresses of the modules (observe
instructions of the modules)
5. Switch on the system
6. Vent the system
7. Set the maximum flow and DHW temperature at the heat
source (observe the operating instructions of the heat
source)
8. Commissioning of the remote controls (observe the
operating instructions of the remote control)
9. Commissioning the Sense II controller (
10. Commissioning the system with the controller
(
11. Check and, if necessary, adjust the settings in the service
menu of the Sense II controller and perform configuration
(e.g. solar) (
12. Remedy warning and fault displays, if necessary, and reset
fault history
13. Name heating circuits (
operating instructions)
14. Complete commissioning reports (
on page 52 and operating instructions)
15. System handover to the end user (
5.2
General commissioning of the Sense II
In the delivered condition of the Sense II the automatic 1-hour
changeover between summer and winter time is activated.
5.3
System commissioning with the
configuration wizard
The controller automatically recognises which BUS devices
(modules e.g. MS100) are installed in the system. The
configuration wizard adjusts the menu and the factory defaults.
The system analysis may take up to one minute.
After the configuration wizard has performed the system
analysis, the
Commissioning
menu is opened. The sub-menus
and settings must be checked here and, if necessary, adjusted
and finally confirmed.
If the system analysis is skipped, the
Commissioning
menu is
opened. The sub-menus and settings listed here must be
carefully adjusted according to the installed system. Finally,
the settings must be confirmed.
Further information on the settings refer to Chapter 7 starting
on page 25.
System schematics are available in the
installation and maintenance instructions of
the MM 100/MM 200 and MS 100/MS 200
modules.
&
Setting language
▶ Turn the selector to select a language and
press the selector.
Setting the date
▶ Turn the selector to set the day, month and
year.
Continue
is highlighted.
▶ If the date is set correctly, press the selector
to apply the date.
Setting the time
▶ Turn the selector to set the hours and the
minutes.
Continue
is highlighted.
▶ If the time is set correctly, press the selector
to apply the time.
&
Low loss header
▶ Turn the selector to set whether a low loss
header is installed or not (temperature
sensor
No low-loss
header
).
System configuration
▶ Turn and press the selector to start (
Yes
) or
to skip the configuration wizard (
No
).
▶ When the configuration wizard is started, the
controller automatically recognises which
BUS nodes are installed in the system
(system analysis) and adjusts the menu and
the factory defaults to the current system.
▶ Perform system commissioning
(
Table 13 General settings at commissioning