Commissioning | 9
5.1
Overview of the commissioning steps
1. Ensure correct installation of Solar heating system
(observe instructions for all assemblies and components)
2. Initial charging with fluids and hydrostatic test
3. Electrical wiring
4. Coding of the modules (observe instructions of the
modules)
5. Fill and vent the system.
6. Commissioning the CS 200 solar controller
(
Chapter 5.2, page 9)
7. Commissioning the system with the solar controller
(
Chapter 5.3, page 9)
8. Check and, if necessary, adjust the settings in the service
menu of the CS 200 solar controller and perform
configuration (
Chapter 5.4, page 11)
9. Remedy warning and fault displays, if necessary, and reset
fault history
10. System handover to end user (
Chapter 5.7, page 11).
5.2
General commissioning of the solar controller
Setting the language
▶ Turn the rotary control knob to select a language and press
the rotary control knob.
Setting the date
▶ Turn the rotary control knob to set the day, month and year.
Continue
is highlighted.
▶ If the date is set correctly, press the rotary control knob to
apply the date.
Setting the time
▶ Turn the rotary control knob to set the hours and the
minutes.
Continue
is highlighted.
▶ If the time is set correctly, press the rotary control knob to
apply the time.
System configuration
▶ Turn and press the rotary control knob to start (
Yes
) or to
skip the configuration wizard (
No
).
▶ When the configuration wizard begins, the solar controller
automatically recognises which BUS nodes (e.g. modules)
are installed in the system (system analysis) and adjusts
the menu and the factory defaults to the current system.
▶ Perform system commissioning (
Chapter 5.3).
5.3
System commissioning with the
configuration wizard
The solar controller automatically recognises which BUS nodes
(e.g. modules) are installed in the system. The configuration
wizard adjusts the menu and the factory defaults.
The system analysis may take up to one minute.
After the configuration wizard has performed the system
analysis, the
Commissioning
menu is opened. The settings
must be checked here and, if necessary, adjusted and finally
confirmed.
If the system analysis is skipped, the
Commissioning
menu is
opened. The settings listed here must be carefully adjusted
according to the installed system. Finally, the settings must be
confirmed.
For further information on the settings refer to the technical
documentation of the modules used.
5.3.1 Commissioning the solar heating system
Menu item
Start configuration wizard?
Question
Answer / setting
Check before starting the configuration wizard:
•
Module installed and address set?
•
Temperature sensor installed?
•
System charged and vented?
Start the configuration
wizard?
Yes | No
Operating mode
Question
Answer / setting
Which system is installed?
Is the coding switch
correspondingly set at the
solar module?
Solar | DHW | Transfer
system | Freshwater station
Extension module
Question
Answer / setting
Is an extension module
installed? (only required if
the use of a MS100 is used
in addition to the required
MS 200)
No | MS 100
Change solar configuration
Question
Answer / setting
Is the solar thermal system
correctly configured with all
functions and additional
functions?
Graphic configuration of the
solar system
Speed ctrl. solar pump
Question
Answer / setting
Is a solar pump with speed
control installed?
No | PWM | 0-10 V
Speed ctrl solar pump2