Installation
3.1
Transport and storage
Page 30
Operating instructions for S 40-3...S 150-3 series screw compressors
Crane transport
Fig. 3.2: Crane transport
Intermediate storage
In case the compressor is not installed immediately after delivery, it must be
stored in a sheltered location. It must be ensured that during the intermediate
storage neither dust nor humidity can get enter.
WARNING!
Improper transportation can damage the compressor. During transport, the
safety covers must not be subjected to any forces or loads.
– Lift the compressor only with the transport pallet provided.
– Protect the compressor with shoring (refer to arrows in the illustration).
– Remove the shoring and transport blocks.
– Use only suitable lifting straps with a minimum length of approx. 315 inch-
es!
Place the loops of the lifting strap under-
neath the compressor transport pallet pro-
vided from one head end to the other.
The loops of the lifting straps must
not
be
attached to the suction filter. Furthermore,
they must
not
be attached to the lug on the
motor.
NOTICE!
In the case of intermediate storage, please observe the specifications and
directions on the permissible environmental influences (see section entitled
"3.2 Compressor room").
We do not accept any liability for damage occurring as a consequence of
improper storage!
In the event of extended intermediate storage you should consult BOGE's
service department.
Following intermediate storage of more than two months, please observe the
instructions for commissioning after an extended standstill (see section en-
titled "3.5 Commissioning").