40

Lay the first roll of felt ensuring the felt is folded over 

the edge as shown above. Ensure a 70mm overhang 

is maintained over both ends. Fix in place with felt 

tacks at 100mm intervals. 

Tools

Step

41

Continue to lay the felt onto the cabin’s roof, 

following the same process listed in step 40, fix the 

felt with felt tacks at 100mm intervals. Ensure an 

overhang of 70mm is present on the front edge. 

Tools

Step

42

Align the fascia’s with the roof and fix into place 

using 30mm nails, making sure to nail through the 

fascia into the log boards. Ensure the felt fold behind 

the fascia board. 

Tools

Step

43

Fold the front of the felt down and line up the facia 

board, using 30mm nails, nail directly through the 

facia board and into the purlins.

Tools

Step

44

To complete your log cabin, affix the door latch into 

place as shown using 30mm screws. Ensure you affix 

the door latch on the exterior of the cabin. 

Tools

Step

45

Congratulations! You have completed the installation 

of your log cabin. Please refer to page 3 of the 

instructions for the required building maintenance for 

the seasonal timber movement. 

Summary of Contents for Mia 19351

Page 1: ...y and retain for future reference Kybotech Claylands Avenue Worksop S81 7BQ 01909 768858 Adult assembly only Minimum 2 people 4 6 Hours building time based on building size and experience CE certi ed...

Page 2: ...01909 768840...

Page 3: ...01909 768840...

Page 4: ......

Page 5: ...01909 768840...

Page 6: ...01909 768840...

Page 7: ...2 Once the outer frame is assembled place the remaining oor bearers as shown ensuring they are equally spaced Fix into position with 50mm screws Pilot Drilling Holes Pilot drill all screw holes to av...

Page 8: ...board and cut to t Tools Step 9 Once you have assembled the oor slide the assembled window frame over the boards resting the frame on top of the log board Ensure this is level and is sitting straight...

Page 9: ...the cabin followed by the full length front wall board Note Review your technical document to check the gable boards used Tools Step 13 Place the nal gable board as shown whilst xing in place with 50m...

Page 10: ...6 Lay the purlins into the slots on the front and rear of the building Screw these in place using 50mm screws by screwing through the board into the purlin on the front and back Please see the technic...

Page 11: ...hinge in the locations marked Af x in place with 30mm screws Tools Step 23 Once you have af xed the door frame on the side of the opening slide the upper frame into position as shown Once in position...

Page 12: ...you place two hinges on the top edge with 30mm screws Tools Step 30 Following the process in stage 28 carefully place the glazing into the window frames and x the glazing beading with 30mm nails Tools...

Page 13: ...or frame opening edges Place the door rebates as shown and x in place with 30mm nails Review the technical document for measurements to cut the rebate to size Tools Step 36 Once complete x the window...

Page 14: ...of and x into place using 30mm nails making sure to nail through the fascia into the log boards Ensure the felt fold behind the fascia board Tools Step 43 Fold the front of the felt down and line up t...

Page 15: ...for you to leave a review at billyoh com and send us pictures of your fully assembled building to billyohcom on Instagram If for whatever reason you are not satis ed with your purchase you have any qu...

Reviews: