10

Following the same process in stage 4, lay the next 

board levels onto the assembly to finalise the base 

walls. Ensure that the boards are level and flush 

with each other as you lay each one.  

Tools

Step

12

Proceed onto the next layer of the gable, by following 

the process in stage 11. Ensure the boards are level 

and are interlocking with one another. Fix in place 

with 50mm screws. 

Tools

Step

11

Place the first gable board on each side wall of the 

cabin, followed by the full length front wall board. 

Note: Review your technical document to check the 

gable boards used. 

Tools

Step

13

Place the final gable board as shown, whilst fixing in 

place with 50mm screws. Ensure your gable is level 

and affixed correctly before proceeding. 

Tools

Step

14

To ensure the window frames are secured into 

position, affix as shown using 30mm screws. Ensure 

your window frame is level before fixing into position.

Tools

Step

15

Begin fixing the framing around all four walls of the 

cabin using 30mm screws. 

 These will need cutting to 

size, therefore, please review the technical document for 

measurements to cut the framing to size. 

Summary of Contents for Mia 19351

Page 1: ...y and retain for future reference Kybotech Claylands Avenue Worksop S81 7BQ 01909 768858 Adult assembly only Minimum 2 people 4 6 Hours building time based on building size and experience CE certi ed...

Page 2: ...01909 768840...

Page 3: ...01909 768840...

Page 4: ......

Page 5: ...01909 768840...

Page 6: ...01909 768840...

Page 7: ...2 Once the outer frame is assembled place the remaining oor bearers as shown ensuring they are equally spaced Fix into position with 50mm screws Pilot Drilling Holes Pilot drill all screw holes to av...

Page 8: ...board and cut to t Tools Step 9 Once you have assembled the oor slide the assembled window frame over the boards resting the frame on top of the log board Ensure this is level and is sitting straight...

Page 9: ...the cabin followed by the full length front wall board Note Review your technical document to check the gable boards used Tools Step 13 Place the nal gable board as shown whilst xing in place with 50m...

Page 10: ...6 Lay the purlins into the slots on the front and rear of the building Screw these in place using 50mm screws by screwing through the board into the purlin on the front and back Please see the technic...

Page 11: ...hinge in the locations marked Af x in place with 30mm screws Tools Step 23 Once you have af xed the door frame on the side of the opening slide the upper frame into position as shown Once in position...

Page 12: ...you place two hinges on the top edge with 30mm screws Tools Step 30 Following the process in stage 28 carefully place the glazing into the window frames and x the glazing beading with 30mm nails Tools...

Page 13: ...or frame opening edges Place the door rebates as shown and x in place with 30mm nails Review the technical document for measurements to cut the rebate to size Tools Step 36 Once complete x the window...

Page 14: ...of and x into place using 30mm nails making sure to nail through the fascia into the log boards Ensure the felt fold behind the fascia board Tools Step 43 Fold the front of the felt down and line up t...

Page 15: ...for you to leave a review at billyoh com and send us pictures of your fully assembled building to billyohcom on Instagram If for whatever reason you are not satis ed with your purchase you have any qu...

Reviews: