background image

Tools

Step

24

Following the process completed in stage 22, repeat 

again with the opposite side door frame. Ensure the 

frame sits flush against the log board. Attach the 

bottom for the door framing with 30mm nails.

Tools

Step

26

Place the barge boards along the top of the Side 

walls, and fix with 30mm screws. Repeat this on the 

other side as well. 

Review the technical document for 

measurements to cut the framing to size. 

Tools

Step

27

To begin the door assembly, lay both sides of the 

door on a surface. Once set, fix the door hinge in the 

locations marked. Affix in place with 30mm screws. 

Tools

Step

23

Once you have affixed the door frame on the side of 

the opening, slide the upper frame into position as 

shown. Once in position, from the inside of the cabin, 

fix in place with 30mm screws. 

Tools

Step

25

On the interior of the cabin place the closure trim against 

the boarding and align with the roof as shown above. Once 

in position, fix each trim into place with 30mm nails. 

Review the technical document for measurements to cut 

the framing to size. 

Tools

Step

22

To affix the door frame into position, push the left door 

frame up against the wall boards as shown. Before 

fixing in place with 30mm screws, ensure the door 

frame sits flat on the floor boards. 

Summary of Contents for Mia 19351

Page 1: ...y and retain for future reference Kybotech Claylands Avenue Worksop S81 7BQ 01909 768858 Adult assembly only Minimum 2 people 4 6 Hours building time based on building size and experience CE certi ed...

Page 2: ...01909 768840...

Page 3: ...01909 768840...

Page 4: ......

Page 5: ...01909 768840...

Page 6: ...01909 768840...

Page 7: ...2 Once the outer frame is assembled place the remaining oor bearers as shown ensuring they are equally spaced Fix into position with 50mm screws Pilot Drilling Holes Pilot drill all screw holes to av...

Page 8: ...board and cut to t Tools Step 9 Once you have assembled the oor slide the assembled window frame over the boards resting the frame on top of the log board Ensure this is level and is sitting straight...

Page 9: ...the cabin followed by the full length front wall board Note Review your technical document to check the gable boards used Tools Step 13 Place the nal gable board as shown whilst xing in place with 50m...

Page 10: ...6 Lay the purlins into the slots on the front and rear of the building Screw these in place using 50mm screws by screwing through the board into the purlin on the front and back Please see the technic...

Page 11: ...hinge in the locations marked Af x in place with 30mm screws Tools Step 23 Once you have af xed the door frame on the side of the opening slide the upper frame into position as shown Once in position...

Page 12: ...you place two hinges on the top edge with 30mm screws Tools Step 30 Following the process in stage 28 carefully place the glazing into the window frames and x the glazing beading with 30mm nails Tools...

Page 13: ...or frame opening edges Place the door rebates as shown and x in place with 30mm nails Review the technical document for measurements to cut the rebate to size Tools Step 36 Once complete x the window...

Page 14: ...of and x into place using 30mm nails making sure to nail through the fascia into the log boards Ensure the felt fold behind the fascia board Tools Step 43 Fold the front of the felt down and line up t...

Page 15: ...for you to leave a review at billyoh com and send us pictures of your fully assembled building to billyohcom on Instagram If for whatever reason you are not satis ed with your purchase you have any qu...