STEP 5
( Powerside Runway Installation )
1. Locate the Powerside Runway easily identified by the
Cylinder and sheave roller mounting structures welded on
the underside. The Powerside Runway will be positioned
on the side of the lift where the power unit is installed.
(See Fig. 5.1)
2. Install Cylinder and Cable Block as shown.
(See Fig. 5.2-5.3)
3. Remove any pre-installed Cable Sheaves from the
Powerside Runway making sure to pay attention to the
order in which they are removed. (This will help at the time
of re-installation.) (See Page 14.)
4. Position the Powerside Runway on top of the Cross
Tubes with the Utility Rail towards the center. The fitting
holes located at the side of the Powerside Runway should
be adjacent to the Power Unit Column. Align the holes in
the runway with the holes on the Cross Tubes and bolt
together using four M12 x 1.75 x 90 hex bolts and washers.
Tighten to 80 ftl/lbs. (See Fig. 5.4)
STEP 6
( Offside Runway Installation )
1. Position the Offside Runway on top of the Cross Tubes
with the Utility Rail located inside. (See Fig. 6.1)
DANGER !
DO NOT PROCEED with Cable installation or go near
the lift work area unless visual confirmation is made of
ALL Safety Locks. ALL locks MUST be engaged before
proceeding. Failure to comply with these instructions may
result in severe personal injury or death. (See page 12.)
Fig 5.1
Fig 5.2
Fig 5.3
Fig 5.4
Fig 6.1
Summary of Contents for HD-14
Page 8: ...8 Assembly View ...
Page 21: ...21 ...
Page 27: ...27 HD 9 12 12X 14 14X Series Rolling Jack Air Line Installation Kit Part 5174009 REV 06 04 09 ...
Page 28: ...28 Adapter Plate Required for HD 9 12 14 Adapter Plate Required for HD 9 12 14 ...
Page 31: ...31 ...
Page 32: ...32 ...
Page 38: ...38 ...