Belfort AWOS Atomic Clock Verification Procedure
06/01/2014
The Belfort AWOS Atomic Clock can be tested, configured and verified using the following
procedure.
Units are typically not shipped with batteries installed. The unit uses 3 AAA batteries. Do
not use rechargeable batteries is this unit.
The unit can be connected to the PC using a USB cable. When connected with the PC, a
7vdc wall pack is also required and supplied.
1.
The cable to the PC and the optional wall pack power supply disconnected, remove
the top 4 cover screws. Open the cover.
2.
If the batteries are not installed, install 3 AAA batteries. Verify the correct battery
polarity during their installation.
3.
Re-install the cover with 4 cover screws.
4.
Connect the USB cable from the PC to the Unit Under Test (UUT).
5.
Connect the unit to the PC with its USB cable and wall pack power supply.
6.
On the PC, start Hyper-terminal (HT) at 9600, 8, N, 1, no handshaking. In HT select
the PC USB Com port that the Atomic Clock is connected to.
7.
In HT, enter the command RN followed by the enter key.
8.
The unit should respond with the unit serial number in the following message format.
Verify that the serial number is correct. If not correct, contact the Belfort Service
Tech or Belfort Factory for directions. If the serial number is received, this means
that communications with the unit is good and the unit is working.
1. N 102
9.
In HT, enter the command RB followed by the enter key. The unit should respond
with the battery voltage in the following message format:
1. B 4.84
10.
The battery voltage can range from 3.5 Vdc to 4.8 Vdc. If the battery voltage is at or
below 3.5v, disconnect the unit from the PC and replace the 3 AAA batteries with
others of the same type. Reconnect the unit to the PC with power and repeat the RB
command.
Summary of Contents for AWOS
Page 17: ... 14 BELFORT INSTRUMENT Proprietary Information Figure 2a Securing the Tower for Maintenance ...
Page 49: ... 46 BELFORT INSTRUMENT Proprietary Information Figure 9 Temperature Humidity Sensor Removal ...
Page 51: ... 48 BELFORT INSTRUMENT Proprietary Information Figure 10 Visibility Sensor Removal ...
Page 60: ...BELFORT INSTRUMENT Proprietary Information Appendix A Belfort AWOS Maintenance Forms ...
Page 66: ...BELFORT INSTRUMENT Proprietary Information This page intentionally left blank ...
Page 74: ...BELFORT INSTRUMENT Proprietary Information Appendix C UHF Transceiver Specifications ...
Page 88: ...BELFORT INSTRUMENT Proprietary Information Appendix F DCP Site Configuration Procedure ...