7. Basic setup procedures
Image 7-41
5. Close the side locking mechanism of the rental tile at the adjoining side by rotating the handle of the side locking mechanism
360º clockwise.
Caution:
Never use adverse force to lock the mechanism.
360º
Image 7-42
6. Repeat from step 1 until all truss beams are joined with each other.
After all truss beams are joined with each other you can proceed with installing the remaining ILite rental tiles
row by row.
After installing one or two rows of ILite rental tiles, realize the data and power cabling for these installed rows,
before lifting the rows further up. These rows are now easy accessible from the work floor.
R5976189 ILITE RENTAL DISPLAY 16/09/2005
61
Summary of Contents for ILite
Page 1: ...ILite rental display Installation manual R5976189 04 16 09 2005...
Page 4: ......
Page 12: ...1 Safety 8 R5976189 ILITE RENTAL DISPLAY 16 09 2005...
Page 16: ...2 Installation requirements 12 R5976189 ILITE RENTAL DISPLAY 16 09 2005...
Page 34: ...5 ILite rental peripherals and accessories 30 R5976189 ILITE RENTAL DISPLAY 16 09 2005...
Page 40: ...6 Setup process of an ILite rental display 36 R5976189 ILITE RENTAL DISPLAY 16 09 2005...
Page 70: ...7 Basic setup procedures 66 R5976189 ILITE RENTAL DISPLAY 16 09 2005...
Page 76: ...8 Cabling of an ILite display 72 R5976189 ILITE RENTAL DISPLAY 16 09 2005...
Page 90: ...10 Servicing 86 R5976189 ILITE RENTAL DISPLAY 16 09 2005...
Page 106: ...B Specifications 102 R5976189 ILITE RENTAL DISPLAY 16 09 2005...