Assemble the track as shown in Figure 3.4.1. The
curve must align and butt up against the vertical
track snugly.
3.4 installing horizontal tracks
¾ track length
equal
equal
¾ track length
Fig: 3.4.1
Before bracing the horizontal tracks, ensure that
they are square to the opening and level. To
check whether your diagonals are equal:
a) Measure from the top of the vertical track to
the end of the opposite horizontal track.
b) Check both sides.
c) Adjust if necessary.
The track support must be located along the
horizontal track approximately at
3
/
4
door height.
d) Calculate the horizontal track brace position as per
section 1.4.2.
e) Measure along the horizontal track to the desired
position and find a structurally sound location to fix
your support to the ceiling or side wall. Fig 3.4.2 or
Fig 3.4.3.
f) Each installation must be assessed individually for
ceiling fixing requirements.
WARNING! Failure to position supports
approximately
3
/
4
door height along the
track can result in the tracks twisting out.
Fig: 3.4.2
WARNING! For all doors higher than 2280mm
and/or wider than 4700mm, or heavier than
110kg, two (2) ceiling supports must be fitted
per horizontal track.
single support
double support
The safety stop must always be fitted to prevent the
panels from accidently exiting the track
g) Install the safety stop
W
at the end of the horizontal
track as shown in Fig 3.4.4.
Fig: 3.4.4
WARNING! The safety stop must be installed.
Failure to do so may cause serious personal
injury or damage to property.
tip
Check that the clearance in the vertical
tracks as per Fig 3.1.2 is also in the
horizontal tracks.
Fig: 3.4.3
NOTE:
Refer to appendix if installing a BTRK for
different cladded doors as they require different
horizontal tracks.