Commissioning
3.1
Safety Instructions
The installation may only be carried out by qualified electricians according to IEC 60204
(International Electrotechnical Commission)-1.
The housing including electronics weighs 41 kg. One Energypack weighs 22 kg. Heavy lifting can cause
a disturbance of the musculoskeletal system.
Lifting the AXIstorage Li SH cover (11 kg) and base (30 kg) separately
If and as necessary, do not lift the AXIstorage Li SH base alone or be sure to use
transport aids.
Risk of crushing and abrasions when lifting and inserting the Energypack.
Use foot and hand protection.
3.2
Installation
3.2.1
Transport
If the installation site is difficult to access, it is recommended that the base and the hood of the
system housing be carried to the installation site separately:
1.
Open the packaging of the AXIstorage Li SH system housing.
2.
Unscrew 2 screws (hexagon socket, SW4) at the front of the bottom of the system
housing
3.
Remove the hood from the system housing base.
4.
Carry the hood and base to the installation site individually.
The Energypack should be transported to the installation site in their original packaging.
3.2.2
Choice of intallation site
The battery system can be mounted upright on the floor.
It is recommended that the inverter be installed on the floor against a wall, where it can be mounted
centrally above the battery system. The inverter should be mounted at least 20 cm above the battery
system. At a distance of up to 30 cm, the cables already attached to the AXIstorage Li SH can be used.
Leave space of at least 30 cm free to the left and right of the battery system to get to the DC
disconnect switch to ensure sufficient air circulation.
To prevent the battery system from tipping over, it can be secured to the installation wall with two
screws (not supplied). Two fixing points are provided in the system housing for this purpose .
Four fixing points are provided in the system housing for wall mounting. Since the battery system can
weigh up to 173 kg, it must be checked in advance whether the wall and fastening material are