16
7.2.5 Installation Recommendation
Note:
•
Before activating the lights, the lights must be laid out on the helipad in the location
they will be installed.
•
Lights should always be installed on mounting plates or stakes.
7.2.5.1 AV-HL-FL range
1.
Install the LED Floodlight Units. See the figure below.
•
Setup a number of concrete pads at equidistant points around the TLOF at
ground level. The concrete pads should have a dimension of approximately 40cm
X 40cm with sufficient depth depending on soil conditions.
•
Note:
As an alternative, it is possible to use rubber tiles instead of concrete pads.
•
Embed 4 bolts. Use the Mount Base as a placing template
•
Make sure the concrete pads are dry and hard before fixing the Mount Base using
washers and screw nuts. Make sure the Mount Base is levelled
•
Point the LED Floodlight Unit into the desired direction.. Make sure the LED
Floodlight Unit is just below 25cm high and levelled. Please see section 7.2.5.2
LED
Floodlight Unit Adjustment
below for further details.
•
If required, tighten the hex sockets at the Frangible Sleeve
Note:
Junction Box not shown for clarity.