AV-HL-FL - Heliport Flood Light
Installation & Service Manual
Latest products and information available at
www.avlite.com
21
AV-HL-FL-PV Only:
3. Install the Solar Assembly for each LED Floodlight Unit. See the figure below.
•
Setup another two concrete pads next to each LED Floodlight Unit, making sure that
the Solar Power Unit is in close proximity to the LED Floodlight Unit/within cable length.
The concrete pads should have a dimension of approximately 40cm x 40cm with
sufficient depth depending on soil conditions. Use the Solar Power Unit and Mount
Base as a placing template.
Note:
As an alternative it is possible to use rubber tiles
instead of concrete pads.
•
Embed 8 bolts. Use the Mount Base as a placing template.
•
Make sure the concrete pads are dry and hard before fixing the Mount Bases using
washers and screw nuts. Make sure the Mount Bases are levelled.
•
Make sure the Solar Power Unit is just below 25cm high and levelled
•
If required, tighten the hex sockets at the Frangible Sleeve
4. Connect the LED Floodlight Unit to the Solar Assembly using the Avlite supplied 2m
long cable.
Note:
Cable glands not shown for clarity.